554-2016 Accept Guaranteed Maximum Price of $152,181,850 from Hoffman Construction Company for the construction of the Washington Park Reservoirs Improvements Project RFP No. 115122 testimony |
D/79366#4 |
05/25/2016 |
|
|
|
554-2016 Accept Guaranteed Maximum Price of $152,181,850 from Hoffman Construction Company for the construction of the Washington Park Reservoirs Improvements Project RFP No. 115122 presentation |
D/79366#3 |
05/25/2016 |
|
|
|
554-2016 Accept Guaranteed Maximum Price of $152,181,850 from Hoffman Construction Company for the construction of the Washington Park Reservoirs Improvements Project RFP No. 115122 additional documents |
D/79366#2 |
05/25/2016 |
|
|
|
554-2016 Accept Guaranteed Maximum Price of $152,181,850 from Hoffman Construction Company for the construction of the Washington Park Reservoirs Improvements Project RFP No. 115122 exhibit |
D/79366#1 |