Records - container:12576 (AF/8305) - 33 records
A2001-008.138 : Under viaduct, looking north at Bent #3, expansion floor-beam, showing faulty concrete [Union Ave]
A2001-008.139 : Looking west from Station "A" with view of south unit complete and stripped, forms for south wing walls in place, beginning hand rail, forms for center unit incomplete [Union Ave, Martin Luther King Jr Blvd]
A2001-008.140 : Looking west from Station "A" with view of completed north unit forms, placing steel, center unit forms under construction, and span over tracks supported on 8"x17" stringers on framed bents [Union Ave]
A2001-008.141 : Looking south from concreting tower with view of forms for center unit incomplete, south unit complete, hand rail begun, base plate of wing walls poured [Union Ave]
A2001-008.142 : Looking from concreting tower down on center unit forms under construction, girder bottoms and part of girder sides in [Union Ave]
A2001-008.143 : Looking north from concreting tower with view of forms for north unit complete, placing steel in same, forms for center unit under construction, "A" frame for hoisting steel to north unit [Union Ave]
A2001-008.144 : Union Ave [Martin Luther King Jr. Ave] looking north near Columbia River
A2001-008.145 : Looking south with view of work on #3 Unit superstructure, concrete pouring stopped at 2:15 pm to straighten reinforcement [Union Ave]
A2001-008.146 : Looking south with view of work on #3 Unit superstructure, roadway slab eighty percent finished at 4:10 pm [Union Ave]
A2001-008.147 : Union Ave [Martin Luther King Jr. Ave] looking north near Columbia River
A2001-008.148 : Looking south at 10:05 am with view of work on #3 Unit superstructure as men stretch wire mesh [Union Ave]
A2001-008.149 : Looking south at 10:45 am with view of work on #3 Unit superstructure as men pour roadway slab [Union Ave]
A2001-008.150 : Looking south at 9:15 am with view of work on #3 Unit superstructure, girders completed [Union Ave]
A2001-008.156 : From north approach, looking south, #3 Unit sidewalk steel in place, base plates north wing walls poured, men working on #2 Unit superstructure forms
A2001-008.155 : From temporary trestle, looking southeast at north abutment, steel in wing walls incomplete, base plates poured, forms for #2 Unit superstructure incomplete [Union Ave]
A2001-008.154 : From south approach, looking north, south wing walls poured, forms for #2 Unit superstructure under construction [Union Ave]
A2001-008.153 : From temporary trestle looking northeast at south abutment, south wing walls poured, #1 Unit hand rail completed except two south panels, showing one lamp post completed without bronze head [Union Ave]
A2001-008.152 : Looking east from Station "B", showing progress of work to date [Union Ave]
A2001-008.151 : Looking west from Station "A", stripping face of north abutment, #2 Unit columns poured, placing additional falsework, superstructure forms nearing completion, bending steel, #1 Unit clearing rubbish [Union Ave]
A2001-008.159 : Looking south at 5:20 pm from north end of #3 Unit with view of work on #2 Unit superstructure, 480 batches poured, pouring sixty - one percent complete [Union Ave]
A2001-008.158 : Looking south at 1:40 pm from north end of #3 Unit with view of work on #2 Unit superstructure, 381 batches poured, pouring forty - nine percent complete [Union Ave]
A2001-008.157 : Looking south at 7:10 am from north end of #3 Unit with view of work on #2 Unit superstructure, 203 batches poured, pouring twenty - six percent complete [Union Ave]
A2001-008.161 : Pouring west sidewalk, finishing coat east sidewalk at 5:00 pm [Union Ave]
A2001-008.160 : East sidewalk just poured, men commencing pour of west sidewalk at 2:30 pm [Union Ave]
A2001-008.164 : Looking west from Station "A" at 4 pm, showing progress of viaduct construction (Union Ave)
A2001-008.163 : From point on fill forty - five degrees north of north abutment, looking south, showing work on deck [Union Ave]
A2001-008.162 : Taken immediately in front of north abutment, looking south, showing floor beams, girders and underside of slab as stripped [Union Ave]
A2001-008.170 : View of east side of viaduct at 2:30 pm, cantilever expansion, Units #1 and 2 showing roughness due to faulty forms [Union Ave]
A2001-008.169 : Columns of bent #2, showing warped condition [Union Ave]
A2001-008.168 : Columns of bent #1, showing warped condition [Union Ave]
A2001-008.167 : #2 Unit floor slabs and girders, bents #4 and #5, showing effect of lining forms with building paper [Union Ave]
A2001-008.166 : View of viaduct looking northeast from south approach to temporary trestle, showing incomplete approach and hand rail [Union Ave]
A2001-008.165 : Union Ave looking south from fill south of south abutment, showing double track used by the Portland Railway, Light & Power Company
«
<