Storm sewer trench layout on Carey Blvd looking south to Willamette Blvd |
06/17/1998 |
|
|
|
S/W forms and AB install on S/S Columbia Ct. |
06/04/1998 |
|
|
|
PGE crew repairing OH neutral cable during paving |
07/09/1998 |
|
|
|
Another view prior to excavation work |
07/23/1998 |
|
|
|
View look N. on N. Carey Blvd from A St. / puddles from heavy shower |
07/30/1998 |
|
|
|
Another view S. tie in work progress looking North |
08/05/1998 |
|
|
|
N. Fessenden St. looking east delamination / lower MH |
08/07/1998 |
|
|
|
Grading and excavation work began today for pond and wetlands by BES |
08/19/1998 |
|
|
|
Gen view of AC existing grades and design S/W grades issues adj. |
09/02/1998 |
|
|
|
S/S Princeton S/W scoring layout |
09/04/1998 |
|
|
|
2 Terex scrapers stripping vegiatation from site and begin N. Berm |
09/16/1998 |
|
|
|
N/S Fessenden forms at trail entry |
09/18/1998 |
|
|
|
PHS 5 ESC , PHS 7 Grading and ESC McKenna below skyline |
11/30/1995 |
|
|
|
PHS 7 Grading for road base |
11/30/1995 |
|
|
|
PHS 7A ESC |
10/31/1995 |