A Legal description for the Dekum Court redevelopment |
02/09/1973 |
|
|
|
Change order No. G-12 for the Dekum Court redevelopment |
02/22/1972 |
|
|
|
Material specifications and requests for substitutes of materials for the Dekum Court redevelopment |
12/31/1971 |
|
|
|
Change order No. G-11 for the Dekum Court redevelopment |
12/28/1971 |
|
|
|
Paperwork for materials stored for Dekum Court redevlopment |
12/12/1971 |
|
|
|
Change order No. G-10 for the Dekum Court redevlopment |
11/30/1971 |
|
|
|
The Schedule of Change Orders for the Dekum Court redevelopment |
10/31/1971 |
|
|
|
A handwritten progress schedule for the Dekum Court redevlopment |
07/31/1971 |
|
|
|
Construction reports for the Dekum Court redevelopment - September through July |
07/15/1971 |
|
|
|
Daily construction report for the Dekum Court redevelopment -July |
07/14/1971 |
|
|
|
Change order No. G-9 for the Dekum Court redevelopment |
07/13/1971 |
|
|
|
Daily construction report for the Dekum Court redevelopment - June |
06/30/1971 |
|
|
|
Change order No. G-8 for the Dekum Court redevelopment |
06/21/1971 |
|
|
|
Daily construction report for the Dekum Court redevelopment - May |
05/31/1971 |
|
|
|
Daily construction reports for the Dekum Court redevelopment - April |
04/30/1971 |