A2000-025.2299 : Men excavating foundation for harbor wall extension for flood control east of NW Front Ave |
05/01/1950 |
|
|
|
A2000-025.2300 : Steel reinforcing for harbor wall extension for flood control under Steel Bridge |
05/15/1950 |
|
|
|
A2000-025.2301 : Men pouring concrete for harbor wall extension for flood control west of SW Front Ave and Glisan St |
05/16/1950 |
|
|
|
A2000-025.2302 : Steel reinforcing for harbor wall extension for flood control east of SW Front Ave and Glisan St |
05/16/1950 |
|
|
|
A2000-025.2303 : Worksite and building materials for harbor wall extension for flood control at NW Front Ave and Glisan St |
05/31/1950 |
|
|
|
A2000-025.2304 : Completed harbor wall extension for flood control at NW Front Ave and Glisan St |
05/31/1950 |
|
|
|
A2000-025.2305 : Men installing steel reinforcing for harbor wall extension for flood control at NW Glisan St between Front and 2nd Aves |
05/01/1950 |
|
|
|
A2000-025.2306 : Excavation foundation for harbor wall extension for flood control at NW Glisan St between Front and 2nd Aves |
05/01/1950 |
|
|
|
A2000-025.2307 : Men excavating for harbor wall extension for flood control at NW Glisan St and Front Ave |
05/08/1950 |
|
|
|
A2000-025.2308 : West view of men excavating for harbor wall extension for flood control by seawall |
05/08/1950 |
|
|
|
A2000-025.2309 : Steel reinforcing for harbor wall extension for flood control looking east from NW Glisan St |
05/08/1950 |
|
|
|
A2000-025.2310 : East view of men setting reinforcing for harbor wall extension for flood control at NW Glisan St and Front Ave |
05/10/1950 |
|
|
|
A2000-025.2311 : West view of men setting reinforcing for harbor wall extension for flood control at NW Glisan St and Front Ave |
05/10/1950 |
|
|
|
A2000-025.2312 : Excavation for harbor wall extension for flood control at NW Glisan St and 3rd Ave |
05/01/1950 |
|
|
|
A2000-025.2313 : Forms and steel reinforcing for harbor wall extension for flood control at NW Glisan St and 3rd Ave |
05/01/1950 |