image

 

Ryan Residence

Addition & Remodel

2891 S.W. Fairview Boulevard

Portland OR 97201

 

MEETING MINUTES

 

 

 

 

Job: #02-24

By: Paul Klein

Meeting: #67 & 68

Date: 16 February 2006

& 23 February 2006

   

Distribution (*attendees)

Phone

Fax

E-mail

*Michael Ryan

503-636-6597

 

mpresq@aol.com

*Marie Ryan

503-636-6597

  

*Andy Mason (Mason Bros.)

503-274-1848

503-274-1852

andy@mason-brothers.com

Jeff Mason (Mason Bros.)

503-274-1848

503-274-1852

jeff@mason-brothers.com

*Josh Grout (Mason Bros.)

503-702-6927

  

Bill Hawkins (WJH Architect)

503-497-9084

503-225-9460

billhawkins@qwest.net

*Paul Klein (WJH Architect))

503-497-9084

503-225-9460

paulklein@qwest.net

 

I.  SCHEDULE

Revised and updated Construction Schedule dated 01-26-06 provided by Contractor.

 

II.  CONTRACT AMOUNT

Base Contract Amount:  $537,425.62

Net Approved CO’s:  $37,111.66  (CO-01 through CO-13)

Contract Total  $574,537.28

 

III.  SUBMITTAL LOG: COMPLETE

 

IV.  CHANGE DIRECTIVES

CD #

Item

Amount

Days

Submitted

Status

01

(CO-10)

Demo & reframe rotten stairwell wall

$4,499.95

 

08-25-05

Approved

02

(CO-01)

Replace cracked foundation wall & underpin existing structure

$2,182.46

 

12-06-04

Approved

03

(CO-03)

Additional excavation & stepped footings

$26,165.50

 

03-02-05

Approved

04

Add serpentine landscape wall

$6,161.87

 

09-16-04

Rejected

05

Add retaining wall at patio

$2,055.77

 

09-23-04

Rejected

06

(CO-04)

Revise electrical bid per revised plans dated 02-08-05

($2,992.63)

 

02-14-05

Approved

07

(CO-01)

Replace entire basement slab

$1,125.38

 

12-06-04

Approved

08

(CO-01)

Add 4’x19’ concrete retaining wall at planter

$2,144.75

 

12-06-04

Approved

09

(CO-02)

Sewer line repair

$4,401.34

 

11-04-04

Approved

10

Refund contingency from CD-09

($209.59)

 

01-21-05

Deleted

11

Add rough-in for central vacuum

$1,805.50

 

02-3-05

Rejected

12

(CO-05)

Add new heating supply ducts to the existing living room

$698.63

 

02-10-05

Approved

13

(CO-08)

Upgrade Bathroom fans

$393.88

 

02-24-05

Approved

14

Add (5) safety valves for gas appliances

$1,150.00

 

02-17-05

Preliminary

15

(CO-05)

Dry rot repairs at SE corner of Living Room

$301.90

 

03-02-05

Approved

16

(CO-05)

Revise roofing specification

($3,628.25)

 

03-24-05

Approved

17

(CO-05)

Eliminate ice & water shield

($692.88)

 

03-24-05

Approved

18

(CO-06)

Revised specifications for fireplaces

($2,489.75)

 

05-05-05

Approved

19

(CO-06)

Revised fireplace venting

($1,495.00)

 

03-24-05

Approved

20

(CO-05)

Add ½” CDX Plywood to existing roof

$3,093.50

 

03-24-05

Approved

21

(CO-09)

Add foundation anchors to existing house

$1,660.34

 

08-11-05

Approved

22

(CO-06)

Framing revisions

$2,098.75

 

03-03-05

Approved

23

(CO-06)

Composition shingle roofing at bay roofs

($2,145.79)

 

04-07-05

Approved

23A

(CO-06)

Add lead flashing around arched windows

$501.98

 

03-31-05

Approved

23B

(CO-06)

Revise roof metal to galvanized

($140.88)

 

04-07-05

Approved

24

(CO-06)

Add doors 08 and 108

$2,134.40

 

03-31-05

Approved

25

Delete stone from 2nd floor balcony; replace with GACO type decking

$523.25

 

01-05-06

Rejected

26

(CO-06)

Replace galvanized ½ round gutters with “K” style gutters

($4,234.30)

 

03-31-05

Approved

27

Omit parking surface; replace with gravel

   

Deleted

28

(CO-10)

Delete hardwood stair treads provide wheatstraw material

(1,437.50)

 

09-01-05

Approved

29

Delete Library cabinets

($9,400)

 

04-7-05

Rejected

30

(CO-12)

Delete Kitchen island

($6,197.57)

 

05-12-05

Approved

31A

Replace shingles on entire house

$3,565.00

 

04-22-05

Rejected

31B

(CO-07)

Replace rotted shingles and misc. damage due to insulation

$2,185.00

 

05-12-05

Approved

31C

Replace shingles affected by blown in insulation

$1,265.00

 

04-22-05

Rejected

31D

Fill insulation holes

$690.00

 

04-22-05

Rejected

32

 

Delete ‘Bluestone’; install ‘Tufflex’ at balcony

($224.25)

 

05-19-05

Approved

33

Add instant water heater to Kitchen sink

   

Deleted

34

(CO-10)

Add (4) lights to the upper kitchen cabinets

$736.00

 

09-28-05

Approved

35

(see 39)

Add copper window well flashing at Office window

$511.75

 

06-07-05

Deleted

36

Delete recirculation system

   

Rejected

37

(CO-11)

Revise Kitchen backsplash tile

$1,136.81

 

08-04-05

Approved

38

Revise shower marble to honed

$1,100.00

 

06-16-05

Rejected

39

(note 1)

Add copper window well flashing at Office window

$395.00

 

08-04-05

Approved

40

Revise fir flooring to white oak, add stain to finish

$2,303.57

 

06-23-05

Rejected

41

Revise select doors to paint grade (quantity to be defined)

   

Deleted

42

(CO-11)

Add decorative balusters main stairway

$614.10

 

07-28-05

Approved

43

(CO-13)

Add back D.S. cleanouts cut without approval (see CD-26)

$345.00

 

07-21-05

Approved

44

Add electro-static finish to interior rail

$525.25

 

07-14-05

Approved

45

(CO-11)

Misc. custom cabinet revisions

$192.00

 

08-18-05

Approved

45A

(CO-11)

Paint custom casework

$8,337.50

 

08-18-05

Approved

46

(CO-12)

Omit marble at library fireplace; replace with alternate marble and bronze frieze

$1,050.25

 

12-08-05

Approved

47

(CO-11)

Revise kitchen counter surface

($559.48)

 

08-04-05

Approved

48

Add master bedroom fireplace surround

$2,311.50

 

08-04-05

Rejected

49

(CO-11)

Add metal grilles to library base cabinets

$718.75

 

09-01-05

Approved

50

Add picture rail to master bedroom

  

08-18-05

Deleted

51

Add lights to elevator closets

  

08-18-05

Deleted

52

(CO-12)

Relocate (8) wall sconce fixtures

$626.75

 

11-10-05

Approved

53

(CO-12)

Delete acid wash

($2,760.00)

 

11-29-05

Approved

54

(CO-12)

Delete cantilever terrace & curve at railing; remove concrete at Living Room bay

($2,199.95)

 

11-29-05

Approved

55

Install trench drain at driveway

$1,371.95

 

11-09-05

Rejected

56

Revise concrete drive to concrete wheel strips & gravel

   

Proposal requested

57

Credit for deletion of concrete corbels per drawings

($575.00)

 

02-16-06

 

58

Install downspout at southwest corner & drain to perforated pipe

$539.73

 

12-08-05

 

59

Additional marble slabs incl. top at Owner furnished table

$2,875.00

 

02-09-06

 

60

New front door hardware

$329.50

 

12-22-05

Approved

61

Add stone surround to Master Bedroom fireplace

$2,415.00

 

01-05-06

 

62

(CO-13)

Powder Room sink

$1,037.07

 

01-05-06

Approved

63

Additional backfill at patio due to over-excavation

$750.00

 

02-02-06

 

64

(CO-12)

Credit to Owner for adjustment to CD-01

($268.35)

 

11-29-05

 
      
      
      

Note 1:  Amount due as reimbursement from Wm. J. Hawkins to Mason Brothers.

 

 

V.  CHANGE ORDER STATUS

C.O. #

CD Items Included

Amount

Days

Date

Status

01

CD-02, 07 & 08

$5,452.59

0

12-09-04

Approved

02

CD-09

$4,401.34

0

01-04-05

Approved

03

CD-03

$26,165.50

0

03-03-05

Approved

04

CD-04

-$2,992.63

0

03-02-05

Approved

05

CD-12, 15, 16, 17 & 20

-$227.10

10

04-01-05

Approved

06

CD-18, 19, 22, 23, 23A, 23B, 24 & 26

-$5,770.59

0

05-05-05

Approved

07

CD-31B

$2,185.00

0

05-12-05

Approved

08

CD-13

$393.88

1

02-24-05

Approved

09

CD-21

$1660.34

2

09-01-05

Approved

10

CD-01, 28, & 34

$3,798.45

5

10-03-05

Approved

11

CD-37, 42 ,45, 45A, 47, & 49

$10,439.68

5

11-25-05

Approved

12

CD-30, 46, 52, 53, 54

& 64

-$9,776.87

(-$9,748.87)

1

12-01-05

Approved

13

CD-43 & 62

$1,382.07

1

01-06-06

Approved

14

     

15

     
      
  

$37,111.66

25

  

 

 

 

VI.  PAYMENT APPLICATION STATUS

Request #

Date received

Amount Due

Paid to Date

Change Orders

01

09-01-04

$11,065.92

0

(None)

02

10-05-04

$32,493.89

$11,065.92

(None)

03

11-04-04

$22,859.66

$43,559.81

(None)

04

12-06-04

$34,503.46

$66,419.47

CO-01

05

1-05-04

$35,093.51

$100,922.93

CO-02

06

02-10-05

$40,083.08

$136,016.44

(None)

07

03-04-05

$67,564.80

$176,099.52

CO-03 & 04

08

04-07-05

$58,607.45

$243,664.32

CO-05

09

05-05-05

$36,611.72

$302,271.77

CO-06

10

06-07-05

$32,627.94

$338,883.49

CO-07

11

07-06-05

$59,308.25

$371,511.43

CO-08

12

08-04-05

$15,534.03

$430,819.68

(None)

13

09-01-05

$42,383.70

$446,353.71

CO-09

14

10-05-05

$35,182.76

$488,737.41

CO-10

15

11-11-05

$17,035.84

$523,920.17

CO-11

16

01-16-06

$3,550.94

$540,956.01

CO-12

17

01-16-06

$1,303.47

$544,506.95

CO-13

18

    
   

$545,810.42

 
 

Total:

$545,810.42

  

Payment applications #01 through #16 are confirmed paid in full. Total paid to date = $544,506.95.

Note: Payment Application #17 exceeds the GMAX for the project. Please note line 9 of form G702 “Balance to finish including retainage” totals $28,726.86. Line 5 of the same form “Retainage” lists the total retainage withheld to date as $28,726.86. It is understood the GMAX amount will be revised as the project is completed, but that the Owner should not make payments to the Contractor in excess of the GMAX (minus the 5% retainage).

 

 

VII.  RFI Log

RFI #01 – #63: (See prior Meeting Minutes)

 

VIII.  JOB SAFETY AND SECURITY ISSUES

(None noted)

 

IX.  MEETING SCHEDULE

1.  Next meeting: 1:00 PM, Thursday, 2 March 2006, at the project site.

 

X.  MEETING NOTES

1.  Contractor furnished HVAC grilles are on site.

2.  Water closet door at Master Bath will not re4cive a door stop.

3.  Water is turned on and running at plumbing fixtures. Master Bath shower fittings are installed.

4.  The junction boxes at the ceiling of the Hall 103 and Laundry 03 are scheduled to receive smoke detectors furnished by Brinks. (Work performed by Brinks is under separate contract with Owner.)

5.  The Contractor will install a permanent handrail at the stairs to the Basement.

 

XI.  ACTION ITEMS

1.  Phone Service and Alarm: Complete

2.  Front Entry Door: Complete

3.  Hazardous Material Removal: Complete

4.  Tree Protection: Complete

5.  Rhododendron Removal: Complete

6.  Planter Box: Complete

7.  Box Hedges: Complete

8.  Electrical Service: Complete

9.  West Stairwell Wall: Issue resolved

10.  Cracked Concrete Wall: Complete

11.  Soils Engineering: Complete

12.  Landscaping and site work: Complete

13.  Site Clearing: Contractor to maintain a clean site.

14.  Sewer Line: Complete

15.  Basement Slab: Complete

16.  Storm Water Removal: Pipes at lower end of house to be re-graded prior to placement of final concrete.

17.  Foundation: Complete

18.  Certified Lumber Products: Complete

19.  Concrete Finish: Complete

20.  Door Hardware: Exterior finish hardware selections complete. Interior finish hardware to be selected with door shop drawings approval.

12-22-05  The Contractor reported that the pocket door hardware selected will not work with the doors. Alternate pocket door hardware was approved. Also, the Owner has decided not to have a privacy latch on the Master Bath door. (Finish hardware is on order.)

21.  Revise Electrical Plan: Complete

22.  Review and Confirm Truss Design: Complete

23.  Carlson Testing: Owners to receive 15% credit for profit & overhead. Contractor to follow up on final letter of approval.

24.  Electrical Utility Charges: Complete (Contractor to pay at end of job.)

03-24-05  Contractor is also responsible for water utility bills. These expenses will be addressed at the end of the project. (Owner to furnish utility billing information to Contractor.)

25.  Rinnai Certification: Complete pending certificate.

02-23-06  Contractor to furnish Owner with required documentation for tax credit.

26.  Recirculation system: Complete

27.  Vacuum systems: Closed, no further action required

28.  Roofing: Complete

29.  Siding:

10-13-05  The wood siding on the house has shown signs of staining. This has been noted on a number of occasions and was observed almost immediately after the exterior paint was applied. Some information regarding extractive bleeding and surfactant bleeding has been forwarded to both the Owner and the Contractor as possible explanations for the problem. The Owner has requested that the shingle material supplier be contacted and a remedy for the problem be proposed.

11-10-05  Contractor provided product literature on the type of paint to used on the shingles and the possible causes of staining. The material is being reviewed.

12-1-05  The Architect requests the shingle supplier come to the site and observe the effects of the apparent extractive bleeding. After reviewing the materials provided by the Contractor it was noted that the latex-based paint was applied in strict accordance with the manufacturers written instructions.

12-08-05  Contractor indicated arrangements would be made for the shingle supplier to visit the site to consider the problem with the shingles.

12-29-05  The Contractor indicated that oil based paint should have been used on the exterior. It was noted that the painter followed the instructions for finish coats supplied by the shingle manufacturer and submitted by the Contractor. The Contractor was responsible for the priming portion of the work. The Contractor supplied a Technical Data Sheet for a “Problem-Solver Wood Cleaner” (attached to these Meeting Minutes).

02-02-06  The Architect tested the tenacity of the tannin stains on the painted shingle surface and discovered that the stains can easily be removed with water and light abrasion, followed by a clean water rinse. It should be possible to remove most or all of the stains with a hose and brush. It is advised that the cleansing of the shingles be performed as soon as possible to avoid increased adhesion of the stain to the surface.

02-23-06  The Contractor will test clean a section of the shingle siding after concrete work at the driveway is complete.

30.  Gas service: Complete

31.  Stair Vault: Complete

32.  Concrete Extras: Waiting for Change Order amount for omitting concrete corbels as specified on the Contract Documents. Skim coating of bad areas of exposed concrete still required.

02-16-06  Contractor delivered Change Directive #57.

33.  Second Floor Supply Ducts (Original): Complete

34.  Exterior Painting: By Owner.

35.  Automatic flue damper: Complete

36.  Audio/Visual: Complete

37.  Install foundation anchors at existing house: Complete

38.  Basement windows # 10: Complete

39.   Electrical at existing house: Complete

40.  Insulation: Complete

41.  Frozen plumbing pipes: Closed

42.  Recycling: Ongoing

43.  Exterior Doors: Complete

44.  Scaffolding: Complete

45.  Gutters:

02-02-06  Contractor to submit revised Change Directive proposal for extension of downspout to connect with storm drain at south side of Living Room chimney (Change Directive #58).

02-23-06  Change directive approved by Owner. Contractor to make final connection to existing storm drain pipe.

46.  Interior Painting: By Owner

47.  Electrical rough-in: Complete

48.  Appliances:

12-29-05  Contractor to provide transition duct to resolve the rough-in conflict with the existing duct location. (HVAC subcontractor to coordinate.)

02-23-06  Appliances waiting for final electrical connections.

49.  Interior trim: Complete

50.  Laundry Room Duct: Complete

51.  Floor finish: Complete

52.  Plumbing Fixtures: Complete

53.  Driveway drainage: Perforated drain pipe approved. Contractor preparing Change Directive proposal approved for revised driveway layout.

02-09-06  Revised driveway grading information to be provided to the Contractor on Friday, 10 February.

54.  Electrical fixtures: Complete

55.  Master Bedroom Fireplace: Complete

56.  Backsplash Tile: Complete

57.  Bath Specialties: Complete

58.  Library cabinet panels: Complete

59.  Interior rail finish: Color selected

60.  Interior paint and stain colors: Complete

61.  Utilities: Complete

62.  Sidewalk and Driveway: The driveway and sidewalk were damaged during the construction of the addition. The City holds the Owner responsible for maintaining sidewalks fronting their property. The necessary repair work to City standards shall be completed by the Contractor.

02-09-06  Sidewalk repairs will coincide with work on new driveway. Concrete subcontractor tentatively scheduled for Monday, 13 February.

02-23-06  Driveway work in progress.

63.  Final Owner selections list: Complete

64.  Allowances:

12-22-05  Owner requests an accounting of the allowances expenditures to date on the project.

02-02-06  Contractor indicated they would update the summary of allowances at the next meeting.

65.  Lien Notices: The Owner has supplied a number of lien notices. The notices are being forwarded to the General Contractor. The Owner is to provide written waivers of Right to Lien from all suppliers and sub-contractors who have issued notices of Right to Lien.

12-08-05  Contractor reported they would obtain waivers of Right to Lien from all sub-contractors and suppliers who have given written notice of Right to Lien.

02-02-06  The Contractor stated that the collection of Lien Releases from suppliers and subcontractors was in progress, and should be complete within the next few weeks.

66.  Energy tax credit: The Owner requests a copy of the approved furnace specification indicating the Manufacturer and the Model Number. The Owner also requests the name of the subcontractor and the date of purchase. Similar information needs to be furnished for the tank-less water heater. (Information to be furnished by the HVAC subcontractor.)

67.  Master Bath water closet door: Complete

68.  Exterior door thresholds: The aluminum thresholds at new exterior doors extend beyond the support of the floor structure. Contractor to provide solid pressure-treated wood blocking between threshold and concrete deck surface to support the threshold.

02-23-06  The threshold support will be installed after the slab at the driveway is poured.