A B
4 May-June  
5   Excavate
6   Pour foundation
7   Build CMU walls @ stair tower
8 July  
9   Frame new addition
10   Install windows @ addition
11   Install new roof
12   Remodel master bedroom
13   Install steel for deck
14 August  
15   New exterior stucco
16   Install new windows in existing home
17   Plumbing rough-in
18   Remodel master bath
19   Electrical rough-in
20   HVAC rough-in
21   Paint exterior of house
22   Install drywall
23   Install patios/decks
24   Install patios/decks handrails
25   Install tile on patios/decks
26 September  
27   Finish drywall
28   Paint interior of addition
29   Break-through into existing kitchen
30   Demo kitchen
31   Install new wood floor on main floor
32   Install carpet in basement and bonus room
33   Install new kitchen cabinets
34 October  
35   Electrical finish
36   Plumbing finish
37   HVAC finish

Sheet1