A |
B |
---|
4 |
May-June |
|
5 |
|
Excavate |
6 |
|
Pour foundation |
7 |
|
Build CMU walls @ stair tower |
8 |
July |
|
9 |
|
Frame new addition |
10 |
|
Install windows @ addition |
11 |
|
Install new roof |
12 |
|
Remodel master bedroom |
13 |
|
Install steel for deck |
14 |
August |
|
15 |
|
New exterior stucco |
16 |
|
Install new windows in existing home |
17 |
|
Plumbing rough-in |
18 |
|
Remodel master bath |
19 |
|
Electrical rough-in |
20 |
|
HVAC rough-in |
21 |
|
Paint exterior of house |
22 |
|
Install drywall |
23 |
|
Install patios/decks |
24 |
|
Install patios/decks handrails |
25 |
|
Install tile on patios/decks |
26 |
September |
|
27 |
|
Finish drywall |
28 |
|
Paint interior of addition |
29 |
|
Break-through into existing kitchen |
30 |
|
Demo kitchen |
31 |
|
Install new wood floor on main floor |
32 |
|
Install carpet in basement and bonus room |
33 |
|
Install new kitchen cabinets |
34 |
October |
|
35 |
|
Electrical finish |
36 |
|
Plumbing finish |
37 |
|
HVAC finish |