2008 State of the River Report Schedule

Revised 8-20-08:

Date

New date

Product/action

August 11

Sept. 5

Rick submits draft text, initial graphics to Ralph

Aug. 22

Sept. 19

Ralph completes 1st layout

10 work days

Aug. 22

Sept. 19

Rick sends 1st layout draft to contributors for review at COB

Sept. 5

Sept. 26

Comments due on 1st layout

5 work days

Sept. 10

Sept. 26

Rick submits changes for 2nd draft to Ralph

3 work days

Sept. 19

Oct. 3

Ralph completes 2nd layout

5 work days

Sept. 19

Oct. 3

2nd layout sent to Gil and Mayor's office @ COB

Sept. 26

Oct. 10

Gil/Mayor complete review, ID changes

5 work days

Sept. 29

Oct. 14

Gil's /Mayor's changes go to Ralph

1 work days

Oct. 1

Oct. 17

Ralph makes Mayor changes and sends final layout to printers

3 work days

October 15

Oct. 31

Reports printed

10 work days to print

 

 

 

OPTIONS FOR FUN-- Revised 9-4-08:

A

New date

Product/action

Sept. 11

Rick submits draft text, initial graphics to Ralph

Sept. 25

Ralph completes 1st layout

10 work days

Sept. 25

Rick sends 1st layout draft to contributors for review at COB

 

Oct. 2

Comments due on 1st layout

5 work days

Oct. 7

Rick submits changes for 2nd draft to Ralph

3 work days

Oct. 14

Ralph completes 2nd layout

5 work days

Oct. 14

2nd layout sent to Gil and Mayor's office @ COB

Oct. 21

Gil/Mayor complete review, ID changes

5 work days

Oct. 22

Gil's /Mayor's changes go to Ralph

1 work days

Oct. 27

Ralph makes Mayor changes and sends final layout to printers

3 work days

Nov. 10

Reports printed

10 work days to print

B

New date

Product/action

Sept. 12

Rick emails Word draft doc to contributors

 

Sept. 12-26

Contributors review draft

10 work days

Sept. 26

Comments due on Word doc

 

Sept. 29-Oct. 1

Rick makes changes

3 work days

Oct. 2

Rick submits draft text, initial graphics to Ralph

 

Oct. 2-16

Ralph works on layout

10 work days

October 16

Ralph completes 1st layout

 

Oct. 17

Rick sends layout draft to contributors/Mayor/Gil

 

Oct. 17-Oct. 24

Layout review

5 work days

Oct. 27-28

Rick marks up changes

2 work days

Oct. 29

Rick submits changes to Ralph

 

Oct. 29-Nov. 3

Ralph finals layout

4 work days

Nov. 3

Ralph submits final to printer

 

Nov. 13

Reports printed

10 work days to print

 

 
 

5 work days

 