2008 State of the River Report Schedule
Revised 8-20-08:
Date | New date | Product/action |
|
August 11 | Sept. 5 | Rick submits draft text, initial graphics to Ralph |
|
Aug. 22 | Sept. 19 | Ralph completes 1st layout | 10 work days |
Aug. 22 | Sept. 19 | Rick sends 1st layout draft to contributors for review at COB |
|
Sept. 5 | Sept. 26 | Comments due on 1st layout | 5 work days |
Sept. 10 | Sept. 26 | Rick submits changes for 2nd draft to Ralph | 3 work days |
Sept. 19 | Oct. 3 | Ralph completes 2nd layout | 5 work days |
Sept. 19 | Oct. 3 | 2nd layout sent to Gil and Mayor's office @ COB |
|
Sept. 26 | Oct. 10 | Gil/Mayor complete review, ID changes | 5 work days |
Sept. 29 | Oct. 14 | Gil's /Mayor's changes go to Ralph | 1 work days |
Oct. 1 | Oct. 17 | Ralph makes Mayor changes and sends final layout to printers | 3 work days
|
October 15 | Oct. 31 | Reports printed | 10 work days to print |
|
|
| |
|
|
| |
|
|
|
OPTIONS FOR FUN-- Revised 9-4-08:
A
New date | Product/action |
|
Sept. 11 | Rick submits draft text, initial graphics to Ralph |
|
Sept. 25 | Ralph completes 1st layout | 10 work days |
Sept. 25 | Rick sends 1st layout draft to contributors for review at COB | |
Oct. 2 | Comments due on 1st layout | 5 work days |
Oct. 7 | Rick submits changes for 2nd draft to Ralph | 3 work days |
Oct. 14 | Ralph completes 2nd layout | 5 work days |
Oct. 14 | 2nd layout sent to Gil and Mayor's office @ COB |
|
Oct. 21 | Gil/Mayor complete review, ID changes | 5 work days |
Oct. 22 | Gil's /Mayor's changes go to Ralph | 1 work days |
Oct. 27 | Ralph makes Mayor changes and sends final layout to printers | 3 work days
|
Nov. 10 | Reports printed | 10 work days to print |
B
New date | Product/action |
|
Sept. 12 | Rick emails Word draft doc to contributors | |
Sept. 12-26 | Contributors review draft | 10 work days |
Sept. 26 | Comments due on Word doc | |
Sept. 29-Oct. 1 | Rick makes changes | 3 work days |
Oct. 2 | Rick submits draft text, initial graphics to Ralph | |
Oct. 2-16 | Ralph works on layout | 10 work days |
October 16 | Ralph completes 1st layout | |
Oct. 17 | Rick sends layout draft to contributors/Mayor/Gil | |
Oct. 17-Oct. 24 | Layout review | 5 work days |
Oct. 27-28 | Rick marks up changes | 2 work days |
Oct. 29 | Rick submits changes to Ralph | |
Oct. 29-Nov. 3 | Ralph finals layout | 4 work days |
Nov. 3 | Ralph submits final to printer | |
Nov. 13 | Reports printed | 10 work days to print |
| ||
| 5 work days | |
| 3 work days |