track 1 |
| track 2 | Product/action | |
Sept. 12 |
| Sept. 12 | Rick submits draft text, initial graphics to Ralph | |
Sept. 12-24 | 10 work days | Sept. 12-19 | 5 work days | Ralph works on 1st layout |
Sept. 24 | Sept. 19 | Ralph completes 1st layout | ||
Sept. 25 |
| Sept. 19 | Rick sends 1st layout draft to contributors for review | |
Sept. 25-Oct. 3 | 7 work days | Sept. 26 | 5 work days | 1st layout review period |
Oct. 3 | Sept. 29 | Comments due on 1st layout | ||
Oct. 6-10 | 5 work days | Sept. 29-Oct. 1 | 3 work days | Rick works on changes to produce 2nd draft layout |
Oct. 13 | 3 work days | Oct. 1 | Rick submits changes for 2nd draft to Ralph | |
Oct. 13-17 | 5 work days | Oct. 1-8 | 5 work days | Ralph creates 2nd draft |
Oct. 20 | Oct. 9 | Rick sends 2nd draft layout to: Gil Mayor Planning Commission Commissioners P&D | ||
Oct. 23 | Oct. 23 | Discussed @ P&D | ||
Oct. 20-24 | 5 work days | Oct. 9-24 | 12 work days | 2nd draft review period |
Oct. 27-31 | 5 work days | Oct. 27-29? | Rick/Ralph complete final draft | |
Nov. 14 | 10 work days to print | Nov. 10-12? | 10 work days to print | Reports printed |
Oct. 28 or Nov. 25 | Planning Commission briefing? | |||
Dec. 3 or 4 | Nov. 26? | Council? | ||
|
| |||
|
| |||
|
|