track 1

track 2

 

Product/action

Sept. 12

Sept. 12

 

Rick submits draft text, initial graphics to Ralph

Sept. 12-24

10 work days

Sept. 12-19

5 work days

Ralph works on 1st layout

Sept. 24

 

Sept. 19

 

Ralph completes 1st layout

Sept. 25

Sept. 19

 

Rick sends 1st layout draft to contributors for review

Sept. 25-Oct. 3

7 work days

Sept. 26

5 work days

1st layout review period

Oct. 3

 

Sept. 29

 

Comments due on 1st layout

Oct. 6-10

5 work days

Sept. 29-Oct. 1

3 work days

Rick works on changes to produce 2nd draft layout

Oct. 13

3 work days

Oct. 1

 

Rick submits changes for 2nd draft to Ralph

Oct. 13-17

5 work days

Oct. 1-8

5 work days

Ralph creates 2nd draft

Oct. 20

 

Oct. 9

 

Rick sends 2nd draft layout to:

Gil

Mayor

Planning Commission

Commissioners

P&D

Oct. 23

 

Oct. 23

 

Discussed @ P&D

Oct. 20-24

5 work days

Oct. 9-24

12 work days

2nd draft review period

Oct. 27-31

5 work days

Oct. 27-29?

 

Rick/Ralph complete final draft

Nov. 14

10 work days to print

Nov. 10-12?

10 work days to print

Reports printed

Oct. 28 or Nov. 25

   

Planning Commission briefing?

Dec. 3 or 4

 

Nov. 26?

 

Council?