A B C D E F G H I J K L M N O
1 ATTACHMENT A: City of Portland                            
2 Metropolitan Transportation Improvement Program (MTIP) 2008-2011         Bike/Trail Ped/Blvd Freight Rd. Const. Bridge Transit TOD Green St.  
3 Projects Recommended for Final Application     Request by Category     $6.90 $11.63 $6.02 $2.00 $2.00 $1.00 $0.22 $3.01 $32.78
4 Project Description MTIP Request (in millions)  
                   
5 Bike/Trail                            
6 1. South/waterfront Greenway Planning and construction of south waterfront greenway-Parks $1.80                        
7 2. Bike Boulevards 20, 50, 70 in NE/SE Portland-PDOT/TRP $3.80                        
8 3. Marine Drive Bike lane and intersection improvements-PDOT/TRP $1.30                        
9 Pedestrian/Boulevard                            
10 4. E. Burnside Implement E. Burnside streetscape Plan-PDOT/PM and PDC $4.70                        
11 5. NE 102rd Ave. NE 102nd Ave. improvements from Glisan to Washington-PDC $1.90                        
12 6. N, NE Killingsworth Phase II-PDOT/PM and PDC $2.10                        
13 7. Sandy Blvd. Streetscape-PAC $0.79                        
14 8. Foster/Woodstock streetscape project Implements Lents Town Center Transportation Plan-PDC & PAC $2.14                        
15 Freight                            
16 9. N. Portland Rd/Columbia Blvd. Intersection Improvements Redesign N. Portland Rd/Columbia Blvd. intersection to channel SB truck traffic on N Portland Rd. onto Columbia Blvd. as the primary truck route to the Rivergate Industrial area and the St. John's Bridge-PDOT/PFC $1.58                        
17 10. N. Burgard St. improvements Widen N. Burgard St. and improve intersections between N. Columbia Blvd. and N. Terminal Rd.-PDOT/PFC $2.70                        
18 11. NE 82nd Ave./Columbia Blvd. Br. Ramp Widen SB ramp from 82nd Ave. to two lanes signalize ramp intersection with Columbia Blvd. and widen Columbia Blvd. to four lanes-Port of Portland/PFC $1.74                        
19 Road Construction/Reconstruction                            
20 12. SE Division St. Implements Division streetscape plan-PDOT/PM $2.00                        
21 Bridge                            
22 13. Morrison Bridge Deck Replacement (Multnomah County) $2.00                        
23 Transit                            
24 14. Eastside Streetcar Construct Eastside Streetcar line-PDOT (Note: This funding would bring total to 2.65 million as intended in congressman Blumenauer's earmark in SAFETEA-LU) $1.00                        
25 Transit Oriented Development (TOD)                            
26 15. Hollywood Transit Center Planning and design for an updated Hollywood Transit Center will address pedestrian and bus access, safety, and connectivity; a special gateway entry to the town center; and opportunites to achieve significant development on site-PDOT/BOP $0.22   Prepared April 4, 2006 [P. Smith]       PAC = Pedestrian Advisory Committee            
27 Green Streets       Revised April 10, 2006 [P. Smith]       PDOT = Portland Office of Transportation            
28 16. Cully Blvd Green St. The Cully Boulevard Green Street Project will plan, design and rebuild NE Cully Boulevard between NE Prescott Street and NE Killingsworth Street using green street design practices.
$3.01   Revised April 13, 2006 [P. Smith]       PDOT/CD = PDOT Civil Design            
29   TOTAL $32.78   Revised April 25, 2006 [P. Smith]       PDOT/PM = PDOT Project Management            
30         Revised April 26, 2006 [P. Smith]       PDOT/TRP = PDOT Transportation Planning            
31         Revised April 28, 2006 [S. Gwin]       PDOT/BTSM = PDOT Bureau of Transportation Systems Management            
32         Revised June 2, 2006 [S. Gwin]       PDC = Portland Development Commission            
33         Revised June 6, 2006 [S. Gwin]       PFC = Portland Freight Committee            
34         Revised June 22, 2006 [S. Gwin]       BOP = Bureau of Planning            

Sheet1