Exhibit A
Project Estimate Confidence Level Rating Index Defined |
COMPLETE | o Final payment made. o Post project assessment completed comparing project estimate, amount of contract award and total amount of change orders issued during project. o Total project costs reported. |
OPTIMAL | Project scope and specifications clearly understood and well defined. o Clear understanding of materials, size and quantities needed to execute job. o Schedule and special site conditions understood. o Project estimate unlikely to change (generally at 90% or greater design and engineering phase). o Total Project contingencies (including project management, design, engineering, plus construction) range between 10%-15%. |
HIGH | Project scope and specifications nearly complete but still subject to change (70%–90% design and engineering phase) o Materials, size and quantities needed to execute job have been defined but subject to minor changes. o Schedule understood. o Total Project contingencies (including project management, design, engineering, plus construction) may range between 20%-30%. |
MODERATE | Project scope defined but lacks details. o Project specifications incomplete (60%-70% design and engineering phase). o Total Project contingencies (including project management, design, engineering, plus construction) may range between 30%-40%. |
LOW | Project scope is a conceptual “vision” with limited detail. o Project cost is an educated guesstimate. Limited technical information available and/or limited analysis performed. o Specifications still in infancy stage. (Less than 50% design and engineering phase). o Total Project contingencies (including project management, design, engineering, plus construction) may range up to or exceed 50%. |