ORDINANCE No. 179900
Authorize a contract with West Yost & Associates for engineering services to prepare a preliminary design report for the upgrade of the Ankeny Wastewater Pump Station, Project No. 7833. (Ordinance)
The City of Portland ordains:
Section 1. The Council finds:
1. The Bureau of Environmental Services has need of a consulting engineering firm to perform complete preliminary design services for the Ankeny wastewater pump station, Project No. 7833.
2. The consultant selection has been conducted in accordance with Chapter 5.68 of the Code of the City of Portland. The consultant selection committee recommends that West Yost & Associates be retained to perform the required professional engineering services.
3. The established cost for preliminary design services is $149,600. Funds are available in the Sewer System Operating Fund, FY 2005-06 Budget, Bureau of Environmental Services, Center Code 145-22-110, Project Number 7833, Account No. 521000.
NOW, THEREFORE, the council directs:
a. The Commissioner of Public Utilities and Auditor are authorized to execute a contract with West Yost & Associates for the purpose described in Section 1, in the amount of $149,600.
b. The Mayor and Auditor are hereby authorized to draw and deliver warrants chargeable to the Sewer System Operating Fund Budget when demand is presented and approved by the proper authority.
Passed by the Council, February 01, 2006 Gary Blackmer
Sam Adams
Commissioner of Public Utilities Auditor of the City of Portland
By /S/ Susan Parsons
Daniel J. Hebert, P.E. (B310)
January 4, 2006 Deputy
145-22-110 / 52100 / 7833 - ord
BACKING SHEET INFORMATION
AGENDA NO. 89 124-2006
ACTION TAKEN:
JANUARY 25, 2006 PASSED TO SECOND READING FEBRUARY 01, 2006 9:30 AM
ORDINANCE/RESOLUTION/COUNCIL DOCUMENT NO. 179900
COMMISSIONERS VOTED AS FOLLOWS: |
YEAS | NAYS | |
ADAMS | X | |
LEONARD | X | |
SALTZMAN | X | |
STEN | X | |
POTTER | X |