A B C E F G
1     ORIG   UNIT TOTAL
2 ITEM DESCRIPTION QUANTITY UNIT PRICE AMOUNT
4 1 Mobilization 1 LS $99,000.00 $99,000.00
5 2 Field Engineering 1 LS $15,000.00 $15,000.00
6 3 Quality Control 1 LS $25,000.00 $25,000.00
7 4 Work Zone Traffic Control 1 LS $21,600.00 $21,600.00
8 5 Preconstruction Services 1 LS $5,000.00 $5,000.00
9 6 Erosion Control 1 LS $1,500.00 $1,500.00
10 7 Track Excavation in Agg. Base 235 CY $20.00 $4,700.00
11 8 Track Excavation in AC (6"-8" AC, Agg.) 10' Wide 935 SY $8.00 $7,480.00
12 9 Track Excavation in Concrete (9" PCC, 4" ATB, Agg.) 10' Wide 165 SY $12.00 $1,980.00
13 10 PCC Roadway Excavation (9" PCC) Outside Track Exc. 165 SY $10.00 $1,650.00
14 11 Remove Existing Curb and Gutter 170 LF $6.00 $1,020.00
15 12 1.52mm PVC Geomembrane (3 meter x 2.5 meter) 10 EA $150.00 $1,500.00
16 13 8" SDR 35 PVC Track Drain Leads 70 LF $120.00 $8,400.00
17 14 Construct Reinforced PCC Pavement (9" Thick) 200 SY $100.00 $20,000.00
18 15 Construct Curb and 18" - 24" Gutter 170 LF $20.00 $3,400.00
19 16 Asphalt Paving Special Staging 1 LS $10,500.00 $10,500.00
20 17 Temporary Asphalt Paving 35 Ton $150.00 $5,250.00
21 18 Furnish Ri59 Head Hardened Girder Rail (HSHM) 220.564 Ton $1,678.29 $370,170.36
22 19 Haul and Unload Materials 1 LS $16,750.00 $16,750.00
23 20 Pre-Bend Tangent Girder Rail 1 LS $3,000.00 $3,000.00
24 21 Install Ri59 Paved Track - Tangent 2,200 TF $317.00 $697,400.00
25 22 Install Ri59 Paved Track - Curved 60 TF $375.00 $22,500.00
26 23 Furnish and Install Track Drain - Ri59 9 EA $2,200.00 $19,800.00
28   Subtotal       $1,362,600.36
30   CM/GC Fee (3.5%)       $47,691.01
32   Total Construction Cost       $1,410,291.37

Sheet1