RESOLUTION No. 36280
Adopt the final capital finance plan for the Portland Streetcar Gibbs Extension Project. (Resolution)
WHEREAS, on August 22, 2003, the Portland Development Commission (PDC) entered into the South Waterfront District Project Development Agreement with Oregon Health & Science University; River Campus Investors, LLC; North Macadam Investors, LLC and Block 39, LLC; and
WHEREAS, the Development Agreement provides for the City to extend the Portland Streetcar to SW Gibbs Street no later than December 2006; and
WHEREAS, Resolution No. 36241, adopted by the City Council on August 4, 2004, recognized the benefits of accelerating the construction of the Portland Streetcar Gibbs Extension Project (Project) in order to realize significant savings; and
WHEREAS, Resolution No. 36241, among other things, adopted the preliminary capital budget for the Portland Streetcar Gibbs Extension Project (Project); and
WHEREAS, on August 4, 2004, the City Council passed Ordinance No. 178654 authorizing an amendment to Agreement No. 31428 with Portland Streetcar, Inc. to provide for completion of design services related to the Project; and
WHEREAS, other services called for in the PSI Agreement No. 31428 include assisting the City in negotiating an amendment to the Construction Contract with Stacy and Witbeck, Inc.(SWI) and assisting the City in negotiating a price for three (3) additional streetcars from the Inekon Group; and
WHEREAS, the design has been completed, SWI and the City have agreed to an amendment to their contract and the cost to construct the Project and the Inekon Group and the City have agreed to an amendment to procure three additional streetcars and the costs to do so; and
WHEREAS, the City and PSI have negotiated an amendment to Agreement No. 31428 for construction management and other services during the construction phase of the Project; and
WHEREAS, all items necessary for the implementation of the Project including previously authorized and completed studies, preliminary and final engineering and design, the purchase of additional vehicles, the related expansion of the maintenance facility, construction and construction management of trackway, stop utility relocations, street work, traffic and train signals and other civil improvements can be provided within the $15.8 million budget; and
WHEREAS, while the sources of funds remain the same, the MTIP funds will be available on approximately July 1, 2005, and $3.3 million in tax increment funds from the Portland Development Commission (PDC) are available now with the balance of $480,000 to be committed only after the South Waterfront Central District Development Agreement Basic Contingencies have been satisfied or otherwise resolved; and
WHEREAS, a temporary loan from the Sewer System Rate Stabilization Fund to the Transportation Operating Fund will provide interim financing until MTIP funds are received by the City and the balance of the tax increment funds are available.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Portland, a municipal corporation of the State of Oregon, the Council adopts the Final Capital Finance Plan for the Portland Streetcar Gibbs Extension Project, as set forth in Exhibit A attached to the original of this Resolution, and by reference made a part hereof.
Adopted by the Council, December 22, 2004
GARY BLACKMER
Commissioner Jim Francesconi Auditor of the City of Portland
Vicky L Diede:slg BY /S/ Susan Parsons
December 15, 2004
RES-Cap Finance-Final.doc DEPUTY
BACKING SHEET INFORMATION
AGENDA NO. 1505-2004
ORDINANCE/RESOLUTION/COUNCIL DOCUMENT NO. 36280
COMMISSIONERS VOTED AS FOLLOWS: |
YEAS | NAYS | |
FRANCESCONI | X | |
LEONARD | === | === |
SALTZMAN | X | |
STEN | X | |
KATZ | X |