A B C D E F G
1 ITEM No. ITEMS OF WORK AND MATERIALS TOTAL QUANT UNIT UNIT PRICE TOTAL PRICE
3   Schedule F - Gibbs Streetcar Extension        
4 1 RFP102328 Preconstruction Services 1 LS $5,000.00 $5,000.00
5 2 Appendix A M/W/ESB Coordinator 1 LS $15,000.00 $15,000.00
6 3 00206 Field Engineering 1 LS $45,000.00 $45,000.00
7 4 00207 Quality Control 1 LS $60,000.00 $60,000.00
8 5 00208 Hazardous Material Health and Safety Plan and Report 1 LS $3,985.00 $3,985.00
9 6 00208 Hazardous Material Disposal 1 PS $85,000.00 $85,000.00
10 7 00210 Mobilization 1 LS $344,028.00 $344,028.00
11 8 00225 Work Zone Traffic Control 1 LS $100,000.00 $100,000.00
12 9 00280 Erosion Control 1 LS $20,000.00 $20,000.00
13 10 00310 Remove Existing Railroad Tracks 1,590 TM(F) $45.00 $71,550.00
14 11 00310 Dispose of Existing Timber Ties 1 PS $15,000.00 $15,000.00
15 12 00310 Removal of AC and Concrete Surfacings (100mm thick) 186 M3(F) $200.00 $37,200.00
16 13 00320 Clearing and Grubbing 1 LS $25,000.00 $25,000.00
17 14 00330 Roadway Excavation (reconstruction) 80 M3 $65.00 $5,200.00
18 15 00330 Track Slab Excavation 108 M3(F) $63.00 $6,804.00
19 16 00330 Track Aggregate Base Excavation 54 M3 $75.00 $4,050.00
20 17 00330 Ballasted Trackbed Excavation 2,000 M3(F) $38.00 $76,000.00
21 18 00330 Ballasted Trackbed Embankment 1,400 M3(F) $25.00 $35,000.00
22 19 00445 200mm SDR 35 PVC Track Drain Leads 15 M $270.00 $4,050.00
23 20 00490 Minor Adjustment of Manholes 1 EA $500.00 $500.00
24 21 00490 Adjusting Water Valves 13 EA $250.00 $3,250.00
25 22 00495 Sewer Trench Resurfacing - Asphalt Concrete 6 M2 $95.00 $570.00
26 23 00620 Cold Plane Pavement Removal 700 M2 $15.00 $10,500.00
27 24 00641 Subgrade Stabilization, Trackway, Roadway 100 M3 $55.00 $5,500.00
28 25 00641 Geotextile Fabric 300 M2 $3.75 $1,125.00
29 26 00641 Subballast Placement 580 M3(F) $37.00 $21,460.00
30 27 00641 Subballast (Imported Material) 1,100 Mg $17.00 $18,700.00
31 28 00641 Trackway Aggregate Base 54 M3 $85.00 $4,590.00
32 29 00641 Aggregate Base for Roadway Construction 50 M3 $140.00 $7,000.00
33 30 00744 Asphalt Concrete Pavement 220 Mg $116.00 $25,520.00
34 31 00757 OCS Pole Foundations F1/FF1 32 EA $2,500.00 $80,000.00
35 32 00757 OCS Pole Foundations F2/FF2 3 EA $3,500.00 $10,500.00
36 33 00759 Curb Cut Spillway 13 EA $700.00 $9,100.00
37 34 00759 Concrete Curbs (outside of stops) 297 M $92.00 $27,324.00
38 35 00759 Track-side Curbs 93 M $140.00 $13,020.00
39 36 00759 Concrete Walks (outside of stops) 53 M2 $62.00 $3,286.00
40 37 00759 Truncated Dome Detectable Warning 6 M2 $300.00 $1,800.00
41 38 00759 Ballast Wall 95 M (F) $180.00 $17,100.00
42 39 00762 Stop Platform (Gibbs) 1 LS $75,000.00 $75,000.00
43 40 00861 Permanent Pavement Marking & Striping 1 LS $15,000.00 $15,000.00
44 41 00905 Signage 1 LS $2,700.00 $2,700.00
45 42 00990 Traffic Signals, Complete (Sheridan & Moody) 1 LS $68,600.00 $68,600.00
46 43 01040 Landscaping 1 LS $26,857.00 $26,857.00
47 44 01120 Irrigation System Water Service 1 LS $6,350.00 $6,350.00
48 45 01120 Irrigation system 1 LS $6,043.00 $6,043.00
49 46 01210 Install Ri52 Paved Track - Tangent 94 TM(F) $793.00 $74,542.00
50 47 01210 Install Ri52 Paved Track - Curved 50 TM(F) $880.00 $44,000.00
51 48 01210 Furnish and Install Track Drain - Ri52 1 EA $2,200.00 $2,200.00
52 49 01210 Install Ri59 to Ri52 Transition Rails 1 PAIR $5,500.00 $5,500.00
53 50 01260 115RE Insulated Rail Joints 3 EA $1,500.00 $4,500.00
54 51 01260 Furnish Concrete Ties 910 EA(F) $90.00 $81,900.00
55 52 01260 Furnish 115RE CWR 1,390 M(F) $115.00 $159,850.00
56 53 01260 Construct Ballasted Track 654 TM(F) $325.00 $212,550.00
57 54 01260 Install Transition Slab to Embedded Track 1 EA $3,000.00 $3,000.00
58 55 01260 Install Road Crossing Rubber Rail Interface 20 TM $460.00 $9,200.00
59 56 01260 Furnish and Install Wheel Stops 2 PAIR $600.00 $1,200.00
60 57 01270 Furnish Refurbished #5 Turnout 1 EA $23,000.00 $23,000.00
61 58 01270 Furnish Powered Switch Mechanism 1 EA $25,000.00 $25,000.00
62 59 01270 Install #5 Turnout Incl. Ties and Switch Mechanism 1 EA $62,000.00 $62,000.00
63 60 01280 Pre-Bend Tangent Rail (Ri52 and 115RE) 1 LS $20,000.00 $20,000.00
64 61 01310 Switch/Rail Bonding 1 LS $7,500.00 $7,500.00
65 62 01330 Ductbank 1 LS $121,979.00 $121,979.00
66 63 01340 SC Manholes 1 LS $37,000.00 $37,000.00
67 64 01366 Moody Train Signal System 1 LS $559,509.00 $559,509.00
68 65 01390 Track Electrical Testing 1 LS $12,571.00 $12,571.00
69 66 16120 Furnish and Install 2kV Feeder Cable, Splices, Termination's, and Supports 1 LS $26,745.00 $26,745.00
70 67 16400 Furnish Taper Tubular Pole PS1, PH1, PF1 24 EA $2,179.00 $52,296.00
71 68 16400 Furnish Taper Tubular Pole PS3, PH3, PF3 6 EA $3,383.00 $20,298.00
72 69 16400 Furnish Taper Tubular Pole PS6, PH6, PF6 2 EA $3,014.00 $6,028.00
73 70 16400 Furnish Taper Tubular Pole PS9, PH9, PF9 3 EA $4,149.00 $12,447.00
74 71 16400 Installation and Grounding of Taper Tubular Poles 35 EA $959.00 $33,565.00
75 72 16400 Furnish and Install Cantilever Assembly 35 EA $3,145.00 $110,075.00
76 73 16400 Furnish and Install Single Track Cross Span Assembly CS1, CS1A 1 EA $10,502.00 $10,502.00
77 74 16400 Furnish and Install Single Track Pull Off Assembly PO1 1 EA $6,640.00 $6,640.00
78 75 16400 Furnish and Install Single Track Backbone Assembly BB1 1 EA $8,660.00 $8,660.00
79 76 16400 Furnish and Install Fixed Termination Assembly FT 2 EA $3,472.00 $6,944.00
80 77 16400 Furnish and Install Single Disconnect Switch Assembly DS1 1 EA $8,857.00 $8,857.00
81 78 16400 Furnish and Install Fixed Tension Single Contact System 902 TM(F) $43.00 $38,786.00
82 79 16950 Subsation Field Acceptance Testing 1 LS $4,399.00 $4,399.00
83 80 16950 OCS Field Acceptance Testing 1 LS $23,243.00 $23,243.00
84 81 16950 Integrated System Testing 1 LS $12,283.00 $12,283.00
85 82 16950 Documentation Drawings and Manuals 1 LS $5,943.00 $5,943.00
87     Total Schedule F   $3,273,974.00
88     CM/GC FEE (3.5%)   $114,589.09
90     TOTAL CONSTRUCTION COST   $3,388,563.09

Bid Items - Track and Civil