A C
1 Uses of Funds  
3 Track, Rail, Roadway, TES  
4 General Construction $3,168,986
5 Rail Procurement $308,041
6 Allowance for Upgrades $300,000
7 Subtotal Track, Rail Roadway, TES $3,777,027
9 Estimating Contingency $566,554
10 Construction Contingency $325,769
11 Design, Management, City Staff (20%) $868,716
12 Subtotal - Contingency and Design $1,761,039
14 Total - Track, Rail, Roadway, TES $5,538,066
16 Vehicles  
17 Purchase 3 Vehicles $6,000,000
18 Inflation/Estimating Contingency (15%) $900,000
19 Inspection/Management $450,000
20 Total - Vehicles $7,350,000
22 Maintenance Yard Improvements $1,940,242
27 Other Misc. Items $275,000
29 Water/Sewer Relocations  
30 Sewer Relocation $200,000
31 Water Relocation $230,718
32 Total Relocations $430,718
34 GRAND TOTAL $15,534,026
37 Sources of Funds  
39 Local Improvement District $2,020,000
40 Tax Increment Financing $3,780,000
41 TriMet Funds - Exchanged for MTIP Funds $10,000,000
43 GRAND TOTAL $15,800,000
45 Surplus / (Gap) $265,974

Sheet1