Exhibit A

 

Proposed Interim Enhanced Security and Infrastructure Investments for Open Reservoirs

 

Phase 1: FY 2004-05.

 

Phase 1 operations and maintenance investments:

•  5 additional contract security staff for onsite patrol of reservoir sites

•  1 additional bureau security staff to provide lead coverage

 

Operations and maintenance costs: approximately $392,000 to be funded from 0.7% of 1.2% in authorized FY 2004-05 rates for reservoir replacement.

 

Phase 1 security and deferred maintenance capital infrastructure investments:

 

Mt. Tabor

•  Video camera and improvements for remote monitoring,

•  Design work for security upgrades to alarms,

•  Design work for remote controls on isolation valves,

•  Upgrades to Reservoir 5 gatehouse to make available as an office facility for security staff and for onsite security monitoring,

•  Sensors to help alert security when critical areas have been breached,

•  Pressure reducing valve (PRV) allowing emergency flow into distribution system if Reservoir 6 needs to be bypassed,

•  Vegetation control to establish clear line of sight around reservoirs perimeter,

•  Signs at trails and on fences encouraging visitors to use paths away from reservoirs,

•  Tennis court net to block errant tennis balls from entering Reservoir 6, and

•  Emergency portable lighting

 

Washington Park

•  Microwave perimeter detection system to help alert security when section of critical area has been breached,

•  Gate improvements and vehicle access controls at entry points to track entry and exit activities,

•  Completion of remote controls installation on isolation valves,

•  Sensors to help alert security when critical areas have been breached,

•  Additional cameras and communications and improvements for remote monitoring and on-site recording, and

•  Improvements to secure buildings

 

Phase 1 includes sidewalk repairs at both reservoir sites to provide a safer walking surface.

 

Security and deferred maintenance capital infrastructure costs: approximately $6.2 million to be funded from reprioritization of current five-year Water Bureau Capital Improvement Plan (no rate impact).

 

 

Preliminary Phase 2 Beginning in FY 2005-06

The Water Bureau proposes a second phase of enhanced security measures and infrastructure investments to be developed and discussed as part of the FY 2005-06 budget process for implementation starting next year. Phase 2 measures would include completion of the installation of remote control isolation valves at Mt. Tabor, additional water quality monitoring instrumentation at the open reservoirs, as well as an environmental technician and instrument technician for ongoing calibration, maintenance and monitoring of these instruments.

 

Based on an evaluation of the effectiveness of the additional security patrols included in Phase 1, Phase 2 could also include proposals to adjust the number of both contract and Water Bureau staff available to provide open reservoir security.

 

FY 04-05 Estimated Capital Improvement Costs for Proposed Phase 1 Interim Security and Deferred Maintenance Measures at Open Reservoirs

Item

Function

Estimated Cost*

Security Improvements

  

Building Security & Camera Improvements at Washington Park

Improves communication, remote viewing and recording of visitation activities, secures buildings

$ 360,000

Communications and video improvements at Tabor

Improves camera communications for monitoring

$ 105,000

 

Begin design of Tabor Security Improvements

Start design work for conduits, alarms, power for security upgrades

$ 150,000

Modify Reservoir 5 Gatehouse interior

Make site available for onsite security monitoring and provides facilities for staff

$ 180,000

Install sensors on ornamental fences at reservoirs

Notifies security when and where reservoirs have been breached

$ 175,000

Install signs at trails and on ornamental fences

Encourages visitors to take other paths away from reservoirs

$ 54,000

Install perimeter detection system at section of Wash. Park outer fence

Notifies security when critical areas have been breached

$ 47,000

Install 2 ornamental pipe gates @ Madison Trail at Wash Park

Blocks area where vehicles can drive into Washington Park reservoir

$ 17,000

Upgrade security gates at Reservoir 3

Improves vehicle control--allows security to track entry and exit

$ 106,000

Vegetation control

Removes nuisance plants and establishes clear line of sight

$ 20,000

Provide emergency portable lighting

Provides security with lighting during night or inclement conditions. Improves security response

$ 20,000

Tennis court net

Blocks errant tennis balls from the courts entering Reservoir 6

$ 36,000

Subtotal

 

$ 1,270,000

   

Deferred Maintenance

  

Pressure reducing valve (PRV) at Tabor

Allows services to be switched to Tabor 411 in an emergency if Reservoir 6 needs to be bypassed

$ 3,172,000

Install electric controls on valves at Wash. Park (including conduits, telemetry, and power)

Allows remote control of isolation valves-- faster emergency response

$ 1,400,000

Sidewalk repairs at reservoir sites

Provides safer walking surface

$ 225,000

Replace sliding gate at Reservoir 4

Replaces failing gate

$ 104,000

Subtotal

 

$ 4,901,000

   

Total

 

$ 6,171,000

 

* All phase 1 projects to be funded from within the current five-year Capital Improvement Plan with no additional rate impact.

 

FY 05-06 Estimated Capital Improvement Costs for Preliminary Phase 2 Interim Security and Deferred Maintenance Measures at Open Reservoirs

 

Item

Function

Cost

Security Improvements

  

Building Security and Camera Improvements at Mt. Tabor

Improves remote viewing and recording of visitation activities, secures buildings

$ 843,000

Provide spot lighting

Provides illumination of dark areas on and around reservoir to improve security response and increase safety for people walking around the reservoirs at night

$ 54,000

Install new sliding gates at Tabor (1 @ Lincoln, 1 @ Res 5 - replace existing pipe gates); Costs include card keys and ornamental finish.

Replace chain at Res 1 with Pipe gate.

Replaces existing manual entry gates with more secure automatic gates. Provides better vehicle control and allows security to track entry and exit activities. Speeds up response time. Replace weak chain with pipe gate.

$ 225,000

Install WQ Monitors (Baseline)

Improves bureaus existing water quality monitoring and establishes baselines to track potential contaminants against.

$ 891,000

Subtotal

 

$ 2,013,000

   

Deferred Maintenance

  

Install valves and electric controls on valves at Tabor (including conduits, telemetry, and power); Site preparation and restoration.

Allows remote control of isolation valves, speeding up emergency response time, increases Bureau’s ability to remote bypass reservoirs and the Tabor site in an emergency

$ 2,420,000

Subtotal

 

$ 2,420,000

   

Total

 

$ 4,433,000

 

Phase 2 projects will be finalized and brought to Council for consideration as part of the FY 2005-06 budget process.