1 The following schedule demonstrates the major work tasks and major milestones for this project and will be the basis for the development of the detailed project plan during the project’s Initiation Phase.
3 Work Plan Description Start Finish
4 Cayenta Utilities Implementation 02/02/04 06/02/06
5 Phase 1 - Project Initiation 02/02/04 03/18/04
6 Milestone - Software Review Checklist Signed Off   02/05/04
7 Phase 2 – Fit Analysis and Configuration 03/08/04 06/25/04
8 Milestone - Delivery of Discovery Document   04/16/04
9 Milestone - Configuration Signed Off   07/13/04
10 Phase 3 - Deployment 01/01/04 12/01/04
11 Milestone - Reports Review Analysis & Sign Off   08/18/04
12 Phase 4 - Functional Testing 06/15/04 12/07/04
13 Milestone - End User Training Plan Delivered   09/07/04
14 Milestone - System Administration Training Delivered   11/26/04
15 Phase 5 - Integrated Testing 12/08/04 07/28/05
16 Milestone - Intergrated Test Plan Signed Off   01/10/05
17 Milestone - Operations Training Delivered   03/21/05
18 Milestone - Batch Process Integration Testing Completed   06/13/05
19 Milestone - Initial Mock Production Milestone Completed   07/05/05
20 Milestone - Integrated Testing - Functional Business Area Signed Off   08/01/05
21 Phase 6 - City Acceptance Testing 07/22/05 09/15/05
22 Milestone - City Acceptance/Non-Acceptance   10/13/05
23 Phase 7 - Production Readiness Evaluation & Cutover 08/12/05 11/17/05
24 Milestone - Live Operation   12/15/05
25 Phase 8 – Post Implementation Support 11/18/05 05/02/06
26 Milestone - Cutover to Standard Support   01/26/06
27 Milestone - On-site Transition Support Second Level (90 days)   03/30/06
28 Milestone - On-site Transition Support Close Off (180 days)   06/02/06
29 Phase 9 -Data Conversion 03/22/04 01/11/06
30 Milestone - Conversion Plan Finalized   06/24/04
31 Milestone - Data Conversion Mock Production Audit #4 Delivered   11/10/05
34 Cycle Simulation Test Planning 08/26/05 11/02/05