EXHIBIT 2
PROJECT SCHEDULE
OHSU/SOUTH WATERFRONT AERIAL TRAM
DESIGN COMPETITION
PORTLAND AERIAL TRANSPORTATION, INC.
JANUARY 8, 2003
Preliminary Competition Schedule
January 8, 2003
Event | Date |
Interviews with 7 firms | Dec 5-6 |
PATI Board decision on final 4 competitors
| Jan 3 |
➢ Notification of final competitors ➢ Transmittal of competition program and background materials to competitors ➢ Arrange for transmittal of competition fees to competitors | Jan 3-6 |
Mandatory “pre-competition” field visit1 Competitors identity “teams”2 Team briefing on scope of design problem; context | Jan 23-24 |
Competition begins | Jan 25 |
➢ Mandatory Portland Visit – Firm 1 – AIA Lecture3 | Jan 30 |
➢ Mandatory Portland Visit – Firm 2 – AIA Lecture | Feb 6 |
➢ Mandatory Portland Visit – Firm 3 – AIA Lecture | Feb 13 |
➢ Mandatory Portland Visit – Firm 4 – AIA Lecture | Feb 20 |
Competitors submit materials | Mar 24 |
Jury convenes – Competitors presentation; Jury develops recommendation to PATI Board | Mar 28 |
PATI Board receives recommendation on final team; authorizes transmittal of recommendation to City Council | Apr 2 |
Presentation to City Council on winning team; request authorization to enter into contract for schematic design | Apr 9 |
PATI negotiate contract for schematic design with winning team | Apr 10 - 21 |
Begin Schematic Design Process | May 1 |
Complete Schematic Designs | Oct 1, 03 |
Present Schematic Design to Council | Oct 8, 03 |