A B C D E F
1 CITY OF PORTLAND, OREGON
2 BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT
3            
4    
     
5            
6            
7            
8            
9            
10            
11 Construction          
12   Copenhagen Utilities & Construction Inc.        
13     Base Contract $2,483,242.00    
14     Changes in Quantities $210,865.25    
15     Change Orders $458,746.79    
16         $3,152,854.04  
17            
18   Construction Claim      
19     Partial Payment $230,056.54    
20     Final Payment $227,980.18    
21     Construction Claim   $458,036.72  
22            
23   Construction Total       $3,610,890.76
24            
25 Engineering          
26   Design Engineering        
27     Street $64,719.16    
28     Stormwater $117,861.82    
29         $182,580.98  
30            
31   Construction Engineering        
32     Street $225,365.88    
33     Stormwater $10,223.70    
34         $235,589.58  
35   Credits        
36     Water Bureau $(17,409.07)    
37     Portland Office of Transportation $(45.08)    
38         $(17,454.15)  
39            
40   Engineering Total       $400,716.41
41            
42 Project Management         $62,624.69
43            
44 SUBTOTAL INCURRED COSTS         $4,074,231.86
45            
46 Auditor's Costs          
47   Advertising     $130.50  
48   LID Construction Fund - Progress Payment Interest through 9/18/02     $1,012,626.37  
49   LID Construction Fund - Interest Credit     $(10,144.57)  
50   LID Construction Fund - Superintendence     $22,236.58  
51           $1,024,848.88
52            
53 Project Management          
54   Project Closeout     $1,877.20  
55   Advertising for Final Assessment Ordinance     $125.00  
56           $2,002.20
57 Overhead          
58   Administrative overhead on project management and engineering @ 23.36%       $108,704.19
59            
60 SUBTOTAL PENDING COSTS         $1,135,555.27
61            
62 TOTAL PROJECT COSTS         $5,209,787.13
63            
64            
65 Property Owner Share          
66   Nauru payment prior to LID formation       $27,520.00
67   Estimated assessment at LID formation   $3,194,644.60    
68   Increase (decrease) from estimated to final assessment   $1,776,079.15    
69   Total property owner billing     $4,970,723.75  
70   Payment from escrow due upon final assessment       $2,949,483.84
71   Total Local Improvement District billing       $2,021,239.91
72 Other Funding          
73   Slide Repair     $38,172.38  
74   Project Closeout     $64,626.89  
75   Other Credit     $39.92  
76   Absorption of Overhead     $108,704.19  
77   Portland Office of Transportation       $211,543.38
78            
79 TOTAL PROJECT FUNDING         $5,209,787.13

Final Estimate