1 | CITY OF PORTLAND, OREGON | |||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||
3 | ||||||
4 |
![]() |
|||||
5 | ||||||
6 | ||||||
7 | ||||||
8 | ||||||
9 | ||||||
10 | ||||||
11 | Construction | |||||
12 | Copenhagen Utilities & Construction Inc. | |||||
13 | Base Contract | $2,483,242.00 | ||||
14 | Changes in Quantities | $210,865.25 | ||||
15 | Change Orders | $458,746.79 | ||||
16 | $3,152,854.04 | |||||
17 | ||||||
18 | Construction Claim | |||||
19 | Partial Payment | $230,056.54 | ||||
20 | Final Payment | $227,980.18 | ||||
21 | Construction Claim | $458,036.72 | ||||
22 | ||||||
23 | Construction Total | $3,610,890.76 | ||||
24 | ||||||
25 | Engineering | |||||
26 | Design Engineering | |||||
27 | Street | $64,719.16 | ||||
28 | Stormwater | $117,861.82 | ||||
29 | $182,580.98 | |||||
30 | ||||||
31 | Construction Engineering | |||||
32 | Street | $225,365.88 | ||||
33 | Stormwater | $10,223.70 | ||||
34 | $235,589.58 | |||||
35 | Credits | |||||
36 | Water Bureau | $(17,409.07) | ||||
37 | Portland Office of Transportation | $(45.08) | ||||
38 | $(17,454.15) | |||||
39 | ||||||
40 | Engineering Total | $400,716.41 | ||||
41 | ||||||
42 | Project Management | $62,624.69 | ||||
43 | ||||||
44 | SUBTOTAL INCURRED COSTS | $4,074,231.86 | ||||
45 | ||||||
46 | Auditor's Costs | |||||
47 | Advertising | $130.50 | ||||
48 | LID Construction Fund - Progress Payment Interest through 9/18/02 | $1,012,626.37 | ||||
49 | LID Construction Fund - Interest Credit | $(10,144.57) | ||||
50 | LID Construction Fund - Superintendence | $22,236.58 |
51 | $1,024,848.88 | |||||
---|---|---|---|---|---|---|
52 | ||||||
53 | Project Management | |||||
54 | Project Closeout | $1,877.20 | ||||
55 | Advertising for Final Assessment Ordinance | $125.00 | ||||
56 | $2,002.20 | |||||
57 | Overhead | |||||
58 | Administrative overhead on project management and engineering @ 23.36% | $108,704.19 | ||||
59 | ||||||
60 | SUBTOTAL PENDING COSTS | $1,135,555.27 | ||||
61 | ||||||
62 | TOTAL PROJECT COSTS | $5,209,787.13 | ||||
63 | ||||||
64 | ||||||
65 | Property Owner Share | |||||
66 | Nauru payment prior to LID formation | $27,520.00 | ||||
67 | Estimated assessment at LID formation | $3,194,644.60 | ||||
68 | Increase (decrease) from estimated to final assessment | $1,776,079.15 | ||||
69 | Total property owner billing | $4,970,723.75 | ||||
70 | Payment from escrow due upon final assessment | $2,949,483.84 | ||||
71 | Total Local Improvement District billing | $2,021,239.91 | ||||
72 | Other Funding | |||||
73 | Slide Repair | $38,172.38 | ||||
74 | Project Closeout | $64,626.89 | ||||
75 | Other Credit | $39.92 | ||||
76 | Absorption of Overhead | $108,704.19 | ||||
77 | Portland Office of Transportation | $211,543.38 | ||||
78 | ||||||
79 | TOTAL PROJECT FUNDING | $5,209,787.13 |