A B C D E F
1 Final Estimate
3 STATEMENT of the various kinds of work performed in the improvement of
5 Lents Phase II LID
7 in accordance with the provisions of Ordinance No. 175259
8 CONTRACTOR: Parker Northwest Paving Company
9
10
11         TOTAL TOTAL
12 NO. ITEMS OF WORK AND MATERIALS UNIT UNIT PRICE QUANTITY AMOUNT
14 1 Mobilization ls $21,856.00 0.87 $19,015.08
15 2 Temporary Protection & Direction of Traffic ls $1,000.00 0.87 $870.00
16 3 Temporary Signs m2 $60.00 15.89 $953.40
17 4 Temporary Barricades ea $110.00 8.00 $880.00
18 5 Temporary Erosion Control ls $1,000.00 0.70 $700.00
19 6 Inlet Protection ea $50.00 8.00 $400.00
20 7 Gravel Construction Entrances ea $300.00 3.00 $900.00
21 8 Removal of Structures & Obtructions ls $1.00 0.00 $-
22 9 Removal of Curbs m $3.30 15.50 $51.15
23 10 Removal of Walks and Driveways m2 $50.00 5.00 $250.00
24 11 Removal of Sound Wall (Bid Only) ls $100.00 0.00 $-
25 12 Clearing and Grubbing ls $18,400.00 0.73 $13,370.23
26 13 Contingent Tree Removal, 0 mm - 200 mm ea $50.00 0.00 $-
27 14 Contingent Tree Removal, 200 mm - 510 mm ea $100.00 0.00 $-
28 15 Contingent Tree Removal, Over 510 mm ea $200.00 0.00 $-
29 16 Exploratory Tree Root Excavation hr $15.00 10.00 $150.00
30 17 General Excavation m3 $12.09 3,441.09 $41,602.78
31 18 300 mm Subgrade Stabilization m2 $2.93 98.20 $287.73
32 19 Subgrade Geotextile m2 $0.60 5,689.00 $3,413.40
33 20 75 mm Drain Pipe m $20.00 0.00 $-
34 21 300 mm Inlet Lead Pipe - Complete m $150.00 41.70 $6,255.00
35 22 Concrete Inlets Type CG-2 ea $650.00 6.00 $3,900.00
36 23 Concrete Inlets Type G-2 ea $650.00 3.00 $1,950.00
37 24 Drainage Curbs, Concrete m $12.30 3.60 $44.28
38 25 Drainage Curbs, Asphalt m $12.30 125.40 $1,542.42
39 26 Adjusting Manholes ea $150.00 3.00 $450.00
40 27 Reconstructing Manholes ea $750.00 3.00 $2,250.00
41 28 Aggregate Base, 200 mm Thick m2 $5.86 4,715.57 $27,633.24
42 29 Standard Duty Class "B" Asphalt Concrete m2 $3.58 5,004.00 $17,914.32
43 30 Standard Duty Class "C" Asphalt Concrete m2 $3.58 4,914.00 $17,592.12
44 31 Asphalt Driveway Connection m2 $18.00 223.14 $4,016.52
45 32 Asphalt Walks m2 $20.00 53.00 $1,060.00
46 33 Concrete Walks m2 $25.09 1,668.50 $41,862.67
47 34 Concrete Driveways m2 $36.15 501.66 $18,135.01
48 35 Concrete Driveway Connection m2 $36.15 92.78 $3,354.00
49 36 Concrete Curb Type C m $23.60 751.94 $17,745.78
50 37 Concrete Curb Type A m $32.80 319.17 $10,468.78
51 38 Remove & Re-install Existing Signs ea $75.00 4.00 $300.00
52 39 Pipe Sign Post ea $50.00 0.00 $-
53 40 Topsoil m3 $29.50 207.33 $6,116.24
54 41 Seeded Lawn m2 $0.55 1,198.50 $659.18
55 42 Bark Mulch m3 $100.00 0.00 $-
56 43 Remove Fence m $5.00 5.50 $27.50
57 44 Remove Post and Cable Fence m $5.00 0.00 $-
58 45 Relocate Mailbox & Post ea $100.00 17.00 $1,700.00
59 46 Install Funding Sign ea $200.00 0.00 $-
60 47 300 mm Storm Sewer Pipe m $150.00 44.70 $6,705.00
61 48 Extra for Pipe Under Pavement m $45.00 7.60 $342.00
62 49 Concrete Manholes, Sedimentation, 3 m Deep ea $1,750.00 5.00 $8,750.00
63 50 Concrete Sumps, 9 m Deep ea $4,500.00 5.00 $22,500.00
64 51 Sed. Manhole in Location of Exist. Sump ea $2,250.00 1.00 $2,250.00
67   TOTAL       $308,367.81
70   CHANGE ORDERS        
71 1 Retaining wall m2 $183.00 45.12 $8,256.96
72 2 Retaining wall m2 $258.00 10.00 $2,580.00
73 4 Additional Mobilization ls $1,000.00 1.00 $1,000.00
78   TOTAL CHANGE ORDERS       $11,836.96
80   TOTAL CONSTRUCTION       $320,204.77
84   APPROVED:        
88   ________________________________________ ______________________________________        
89   CONTRACTOR Date CONTRACT MANAGER Date

Final Estimate - Lents II