A B C D E F
1 CITY OF PORTLAND, OREGON
2 BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT
3            
4    
     
5            
6            
7            
8            
9            
10            
11 Construction          
12   Parker Northwest Paving Company        
13     Contract   $308,367.81  
14     Change Order #1: Retaining Wall   $8,256.96  
15     Change Order #2: Retaining Wall   $2,580.00  
16     Change Order #3: Additional Mobilization   $1,000.00  
17   Construction Total     $320,204.77  
18            
19 Engineering          
20   Design Engineering     $95,506.01  
21   Construction Engineering     $30,777.13  
22   Engineering Total     $126,283.14  
23            
24 Project Management       $52,025.67  
25            
26 SUBTOTAL INCURRED COSTS (already billed to PDC)         $498,513.58
27            
28 Auditor's Costs          
29   LID Construction Fund - Progress Payment Interest through 7/03/02     $4,942.54  
30   LID Construction Fund - Superintendence     $2,205.14  
31   Recording     $1,260.00  
32         $8,407.68  
33            
34 Construction          
35   Bureau of Environmental Services     $4,346.63  
36   J.P. Contractors, Inc. (street trees)     $31,441.59  
37         $35,788.22  
38            
39 Project Management          
40   Advertising for Time & Manner Ordinance     $125.00  
41   Project Closeout     $2,564.36  
42         $2,689.36  
43            
44 Overhead          
45   Administrative overhead on project management and engineering @ 40.00%     $72,349.27  
46         $72,349.27  
47            
48 SUBTOTAL ESTIMATED COSTS (to be billed to PDC under terms of I.A.A.)         $119,234.53
49            
50 TOTAL PROJECT COSTS         $617,748.11
51            
52            
53 Property Owner Share          
54   Estimated assessment at LID formation     $260,757.68  
55   Increase (decrease) from estimated to final assessment     $-  
56   Final assessment     $260,757.68  
57            
58   Recording fees     $1,260.00  
59   Total Local Improvement District billing       $262,017.68
60            
61 Other Funding          
62   Portland Development Commission     $323,884.64  
63   Portland Office of Transportation (FY2000 & FY2001 overhead)     $31,845.79  
64           $355,730.43
65            
66 TOTAL PROJECT FUNDING         $617,748.11

Final Estimate Lents II