A | B | C | D | E | F | |
---|---|---|---|---|---|---|
1 | Final Estimate | |||||
3 | STATEMENT of the various kinds of work performed in the improvement of | |||||
5 | Lents Phase I LID | |||||
7 | in accordance with the provisions of Ordinance No. 175258 | |||||
8 | CONTRACTOR: Parker Northwest Paving Company | |||||
9 | ||||||
10 | ||||||
11 | TOTAL | TOTAL | ||||
12 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
14 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 |
15 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 |
16 | 3 | Temporary Signs | m2 | $60.00 | 25.92 | $1,555.20 |
17 | 4 | Temporary Barricades | ea | $110.00 | 13.00 | $1,430.00 |
18 | 5 | Flaggers | hr | $15.00 | 61.00 | $915.00 |
19 | 6 | Temporary Erosion Control | ls | $500.00 | 0.50 | $250.00 |
20 | 7 | Inlet Protection | ea | $50.00 | 0.00 | $- |
21 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 |
22 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 0.00 | $- |
23 | 10 | Removal of Curbs | m | $3.30 | 46.35 | $152.96 |
24 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 35.50 | $275.13 |
25 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 |
26 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 |
27 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 0.00 | $- |
28 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 2.00 | $200.00 |
29 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 |
30 | 17 | General Excavation | m3 | $12.09 | 4,516.93 | $54,609.68 |
31 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 105.95 | $310.43 |
32 | 19 | Subgrade Geotextile | m2 | $0.60 | 5,438.03 | $3,262.82 |
33 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 108.00 | $16,200.00 |
34 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 10.00 | $351.70 |
35 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 0.00 | $- |
36 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 |
37 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 19.00 | $12,350.00 |
38 | 25 | Adjust Manholes | ea | $150.00 | 4.00 | $600.00 |
39 | 26 | Reconstructing Manholes | ea | $750.00 | 4.00 | $3,000.00 |
40 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5,418.65 | $31,753.29 |
41 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5,784.00 | $20,244.00 |
42 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 6,064.39 | $21,225.37 |
43 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 413.45 | $7,442.10 |
44 | 31 | Asphalt Sidewalk | m2 | $13.55 | 50.76 | $687.80 |
45 | 32 | Concrete Walks | m2 | $25.09 | 2,295.98 | $57,606.24 |
46 | 33 | Concrete Driveways | m2 | $36.15 | 939.46 | $33,961.41 |
47 | 34 | Concrete Driveway Connection | m2 | $36.15 | 297.52 | $10,755.42 |
48 | 35 | Concrete Curb Type A | m | $32.80 | 510.80 | $16,754.24 |
49 | 36 | Concrete Curb Type C | m | $23.60 | 951.22 | $22,448.79 |
50 | 37 | Concrete Steps | m | $90.00 | 2.96 | $266.40 |
51 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 5.00 | $375.00 |
52 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 0.00 | $- |
53 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 0.00 | $- |
54 | 41 | Topsoil | m3 | $29.50 | 333.00 | $9,823.50 |
55 | 42 | Seeded Lawn | m2 | $0.55 | 1,871.00 | $1,029.05 |
---|---|---|---|---|---|---|
56 | 43 | Bark Mulch | m3 | $100.00 | 0.00 | $- |
57 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 39.60 | $1,298.88 |
58 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 3.00 | $75.00 |
59 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 39.00 | $3,900.00 |
60 | 47 | Install Funding Sign | ea | $200.00 | 0.00 | $- |
61 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.66 | $11,499.00 |
62 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 8.00 | $281.36 |
63 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 10.00 | $17,500.00 |
64 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 0.00 | $- |
65 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 |
66 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 |
67 | 54 | Abandon Sump | ea | $300.00 | 0.00 | $- |
70 | TOTAL | $447,374.75 | ||||
73 | CHANGE ORDERS | |||||
74 | 1 | Retaining wall | m2 | $183.00 | 10.65 | $1,948.95 |
79 | TOTAL CHANGE ORDERS | $1,948.95 | ||||
81 | TOTAL CONSTRUCTION | $449,323.70 | ||||
85 | APPROVED: | |||||
89 | _______________________________________ ______________________________________ | |||||
90 | CONTRACTOR Date CONTRACT MANAGER Date |
A | B | C | D | E | F | G | |
---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | ||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | ||||||
3 | |||||||
4 | BID TABULATION | ||||||
5 |
![]() |
||||||
6 | |||||||
7 | |||||||
8 | |||||||
9 | |||||||
10 | |||||||
11 | CONTRACTOR: Parker Northwest Paving Company | ||||||
12 | |||||||
13 | ###### PROPOSAL "A" _ STREET ITEMS ###### | ||||||
14 | |||||||
15 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | TOTAL QUANTITY | UNIT PRICE | TOTAL AMOUNT | |
16 | |||||||
17 | 1 | Mobilization | ls | 1.00 | $17,000.00 | $17,000.00 | |
18 | 2 | Temporary Protection & Direction of Traffic | ls | 1.00 | $1,000.00 | $1,000.00 | |
19 | 3 | Temporary Signs | m2 | 7.77 | $60.00 | $466.20 | |
20 | 4 | Temporary Barricades | ea | 14.00 | $110.00 | $1,540.00 | |
21 | 5 | Flaggers | hr | 80.00 | $15.00 | $1,200.00 | |
22 | 6 | Temporary Erosion Control | ls | 1.00 | $500.00 | $500.00 | |
23 | 7 | Inlet Protection | ea | 25.00 | $50.00 | $1,250.00 | |
24 | 8 | Gravel Entrance | ea | 14.00 | $1,200.00 | $16,800.00 | |
25 | 9 | Removal of Structures & Obstructions | ls | 1.00 | $1.00 | $1.00 | |
26 | 10 | Removal of Curbs | m | 93.40 | $3.30 | $308.22 | |
27 | 11 | Removal of Walks and Driveways | m2 | 145.70 | $7.75 | $1,129.18 | |
28 | 12 | Removal of Inlets | ea | 5.00 | $25.00 | $125.00 | |
29 | 13 | Clearing and Grubbing | ls | 1.00 | $2,100.00 | $2,100.00 | |
30 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | 1.00 | $10.00 | $10.00 | |
31 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | 1.00 | $100.00 | $100.00 | |
32 | 16 | Exploratory Tree Root Excavation | hr | 10.00 | $1.00 | $10.00 | |
33 | 17 | General Excavation | m3 | 4372.00 | $12.09 | $52,857.48 | |
34 | 18 | 300mm Subgrade Stabilization | m2 | 2788.00 | $2.93 | $8,168.84 | |
35 | 19 | Subgrade Geotextile | m2 | 5574.00 | $0.60 | $3,344.40 | |
36 | 20 | 300mm Inlet Pipe, Complete | m | 112.80 | $150.00 | $16,920.00 | |
37 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | 24.00 | $35.17 | $844.08 | |
38 | 22 | 75mm Drain Pipe (Bid Only) | m | 10.00 | $20.00 | $200.00 | |
39 | 23 | Concrete Inlets Type G-1 | ea | 1.00 | $650.00 | $650.00 | |
40 | 24 | Concrete Inlets Type CG-2 | ea | 15.00 | $650.00 | $9,750.00 | |
41 | 25 | Adjust Manholes | ea | 2.00 | $150.00 | $300.00 | |
42 | 26 | Reconstructing Manholes | ea | 2.00 | $750.00 | $1,500.00 | |
43 | 27 | Aggregate Base (200mm Thick) | m2 | 5574.00 | $5.86 | $32,663.64 | |
44 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | 5574.00 | $3.50 | $19,509.00 | |
45 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | 5574.00 | $3.50 | $19,509.00 | |
46 | 30 | Asphalt Driveway Connections | m2 | 154.10 | $18.00 | $2,773.80 | |
47 | 31 | Asphalt Sidewalk | m2 | 76.00 | $13.55 | $1,029.80 | |
48 | 32 | Concrete Walks | m2 | 2208.00 | $25.09 | $55,398.72 | |
49 | 33 | Concrete Driveways | m2 | 684.30 | $36.15 | $24,737.45 | |
50 | 34 | Concrete Driveway Connection | m2 | 173.70 | $36.15 | $6,279.26 |
51 | 35 | Concrete Curb Type A | m | 488.70 | $32.80 | $16,029.36 | |
---|---|---|---|---|---|---|---|
52 | 36 | Concrete Curb Type C | m | 863.00 | $23.60 | $20,366.80 | |
53 | 37 | Concrete Steps | m | 4.80 | $90.00 | $432.00 | |
54 | 38 | Remove & Re-install Existing Signs | ea | 9.00 | $75.00 | $675.00 | |
55 | 39 | Sign Support Footings (Bid Only) | ea | 1.00 | $75.00 | $75.00 | |
56 | 40 | Pipe Sign Posts (Bid Only) | ea | 1.00 | $15.00 | $15.00 | |
57 | 41 | Topsoil | m3 | 331.00 | $29.50 | $9,764.50 | |
58 | 42 | Seeded Lawn | m2 | 1871.00 | $0.55 | $1,029.05 | |
59 | 43 | Bark Mulch | m3 | 1.00 | $100.00 | $100.00 | |
60 | 44 | Removing & Rebuilding Fence (Bid Only) | m | 20.00 | $32.80 | $656.00 | |
61 | 45 | Replacement Mailboxes (Bid Only) | ea | 5.00 | $25.00 | $125.00 | |
62 | 46 | Relocate Mailbox with new Post | ea | 43.00 | $100.00 | $4,300.00 | |
63 | 47 | Install Funding Sign | ea | 5.00 | $200.00 | $1,000.00 | |
64 | |||||||
65 | |||||||
66 | TOTAL PROPOSAL "A" | $354,542.77 | |||||
67 | |||||||
68 | |||||||
69 | ###### PROPOSAL "B" STORM SEWER ITEMS ###### | ||||||
70 | |||||||
71 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | TOTAL QUANTITY | UNIT PRICE | TOTAL AMOUNT | |
72 | |||||||
73 | 48 | 300mm Storm Sewer Pipe, Complete | m | 76.20 | $150.00 | $11,430.00 | |
74 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | 31.00 | $35.17 | $1,090.27 | |
75 | 50 | Sedimentation Manholes, 3 m Deep | ea | 9.00 | $1,750.00 | $15,750.00 | |
76 | 51 | Sed. Manhole in Location of Exist. Sump | ea | 1.00 | $2,250.00 | $2,250.00 | |
77 | 52 | Concrete Sumps, 9m Deep | ea | 10.00 | $4,500.00 | $45,000.00 | |
78 | 53 | Abandon Manhole | ea | 1.00 | $300.00 | $300.00 | |
79 | 54 | Abandon Sump | ea | 1.00 | $300.00 | $300.00 | |
80 | |||||||
81 | |||||||
82 | TOTAL PROPOSAL "B" | $76,120.27 | |||||
83 | |||||||
84 | |||||||
85 | |||||||
86 | GRAND TOTAL PROPOSALS "A" + "B" | $430,663.04 | |||||
87 | |||||||
88 | |||||||
89 | CITY ENGINEER'S ESTIMATE: |
![]() |
|||||
90 | $705,247.38 | ||||||
91 | CONTRACTOR'S PERCENTAGE OF | ||||||
92 | CITY ENGINEER'S ESTIMATE: | ||||||
93 | 61% |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 7 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 100% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.80 | $800.00 | 80% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 334% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 93% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 28.00 | $420.00 | 35% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.50 | $250.00 | 50% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 14.00 | $16,800.00 | 100% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 33.35 | $110.06 | 36% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 5.00 | $125.00 | 100% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 1.00 | $2,100.00 | 100% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 0% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 200% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 100% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 4,240.84 | $51,271.76 | 97% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 4% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 5,438.03 | $3,262.82 | 98% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 71.40 | $10,710.00 | 63% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 11.00 | $7,150.00 | 73% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 1.00 | $150.00 | 50% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 4.00 | $3,000.00 | 200% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 4,906.95 | $28,754.73 | 88% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 3,428.60 | $12,000.10 | 62% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 3,428.60 | $12,000.10 | 62% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 21.33 | $383.94 | 14% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 1,881.77 | $47,213.71 | 85% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 715.46 | $25,863.81 | 105% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 222.28 | $8,035.49 | 128% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 510.80 | $16,754.24 | 105% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 951.22 | $22,448.79 | 110% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 2.96 | $266.40 | 62% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 333.00 | $9,823.50 | 101% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 60.00 | $6,000.00 | 140% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 48.00 | $7,200.00 | 63% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 8.00 | $281.36 | 26% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 9.00 | $15,750.00 | 100% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 10.00 | $45,000.00 | 100% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 1.00 | $300.00 | 100% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $374,731.43 | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $374,731.43 | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 9 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.80 | $800.00 | 0.20 | $200.00 | 1.00 | $1,000.00 | 2 | 100% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 41.00 | $615.00 | 20.00 | $300.00 | 61.00 | $915.00 | 5 | 76% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 14.00 | $16,800.00 | 0.00 | $- | 14.00 | $16,800.00 | 8 | 100% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 33.35 | $110.06 | 13.00 | $42.90 | 46.35 | $152.96 | 10 | 50% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 35.50 | $275.13 | 35.50 | $275.13 | 11 | 24% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 1.00 | $2,100.00 | 0.00 | $- | 1.00 | $2,100.00 | 13 | 100% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 4,240.84 | $51,271.76 | 276.09 | $3,337.93 | 4,516.93 | $54,609.68 | 17 | 103% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 5,438.03 | $3,262.82 | 0.00 | $- | 5,438.03 | $3,262.82 | 19 | 98% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 75.40 | $11,310.00 | 32.60 | $4,890.00 | 108.00 | $16,200.00 | 20 | 96% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 10.00 | $351.70 | 10.00 | $351.70 | 21 | 42% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 1.00 | $650.00 | 0.00 | $- | 1.00 | $650.00 | 23 | 100% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 15.00 | $9,750.00 | 4.00 | $2,600.00 | 19.00 | $12,350.00 | 24 | 127% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 1.00 | $150.00 | 3.00 | $450.00 | 4.00 | $600.00 | 25 | 200% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 4.00 | $3,000.00 | 0.00 | $- | 4.00 | $3,000.00 | 26 | 200% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 4,906.95 | $28,754.73 | 511.70 | $2,998.56 | 5,418.65 | $31,753.29 | 27 | 97% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 5,684.00 | $19,894.00 | 100.00 | $350.00 | 5,784.00 | $20,244.00 | 28 | 104% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 5,684.00 | $19,894.00 | 380.39 | $1,331.37 | 6,064.39 | $21,225.37 | 29 | 109% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 127.56 | $2,296.08 | 285.89 | $5,146.02 | 413.45 | $7,442.10 | 30 | 268% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 50.76 | $687.80 | 0.00 | $- | 50.76 | $687.80 | 31 | 67% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,881.77 | $47,213.71 | 414.21 | $10,392.53 | 2,295.98 | $57,606.24 | 32 | 104% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 715.46 | $25,863.81 | 224.00 | $8,097.60 | 939.46 | $33,961.41 | 33 | 137% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 222.28 | $8,035.49 | 75.24 | $2,719.93 | 297.52 | $10,755.42 | 34 | 171% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 510.80 | $16,754.24 | 0.00 | $- | 510.80 | $16,754.24 | 35 | 105% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 951.22 | $22,448.79 | 0.00 | $- | 951.22 | $22,448.79 | 36 | 110% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 5.00 | $375.00 | 5.00 | $375.00 | 38 | 56% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 333.00 | $9,823.50 | 0.00 | $- | 333.00 | $9,823.50 | 41 | 101% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 1,871.00 | $1,029.05 | 1,871.00 | $1,029.05 | 42 | 100% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 39.60 | $1,298.88 | 0.00 | $- | 39.60 | $1,298.88 | 44 | 198% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 3.00 | $75.00 | 0.00 | $- | 3.00 | $75.00 | 45 | 60% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 39.00 | $3,900.00 | 0.00 | $- | 39.00 | $3,900.00 | 46 | 91% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 76.66 | $11,499.00 | 0.00 | $- | 76.66 | $11,499.00 | 48 | 101% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 10.00 | $17,500.00 | 0.00 | $- | 10.00 | $17,500.00 | 50 | 111% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 10.00 | $45,000.00 | 0.00 | $- | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $402,487.05 | $44,887.71 | $447,374.75 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | 1 | Retaining wall | m2 | $183.00 | 25.00 | $4,575.00 | 0.00 | $- | 10.65 | $1,948.95 | 10.65 | $1,948.95 | CO1 | #VALUE! | |
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $4,575.00 | $- | $1,948.95 | $1,948.95 | ||||||||||
73 | TOTAL ALL ITEMS | $435,238.04 | $402,487.05 | $46,836.66 | $449,323.70 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 103% | |||||||||||||
79 | 5% RETAINAGE | $20,124.35 | $2,341.83 | $22,466.18 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $44,494.83 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $46,836.66 | amounting to | $44,494.83 | |||||||||||
86 | This certificate is for work completed through : | March 15, 2002. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 8 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.80 | $800.00 | 0.00 | $- | 0.80 | $800.00 | 2 | 80% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 41.00 | $615.00 | 0.00 | $- | 41.00 | $615.00 | 5 | 51% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 14.00 | $16,800.00 | 0.00 | $- | 14.00 | $16,800.00 | 8 | 100% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 33.35 | $110.06 | 0.00 | $- | 33.35 | $110.06 | 10 | 36% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 1.00 | $2,100.00 | 0.00 | $- | 1.00 | $2,100.00 | 13 | 100% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 4,240.84 | $51,271.76 | 0.00 | $- | 4,240.84 | $51,271.76 | 17 | 97% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 5,438.03 | $3,262.82 | 0.00 | $- | 5,438.03 | $3,262.82 | 19 | 98% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 75.40 | $11,310.00 | 0.00 | $- | 75.40 | $11,310.00 | 20 | 67% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 1.00 | $650.00 | 0.00 | $- | 1.00 | $650.00 | 23 | 100% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 15.00 | $9,750.00 | 0.00 | $- | 15.00 | $9,750.00 | 24 | 100% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 1.00 | $150.00 | 0.00 | $- | 1.00 | $150.00 | 25 | 50% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 4.00 | $3,000.00 | 0.00 | $- | 4.00 | $3,000.00 | 26 | 200% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 4,906.95 | $28,754.73 | 0.00 | $- | 4,906.95 | $28,754.73 | 27 | 88% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 5,675.60 | $19,864.60 | 8.40 | $29.40 | 5,684.00 | $19,894.00 | 28 | 102% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 5,675.60 | $19,864.60 | 8.40 | $29.40 | 5,684.00 | $19,894.00 | 29 | 102% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 62.23 | $1,120.14 | 65.33 | $1,175.94 | 127.56 | $2,296.08 | 30 | 83% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 39.20 | $531.16 | 11.56 | $156.64 | 50.76 | $687.80 | 31 | 67% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,881.77 | $47,213.71 | 0.00 | $- | 1,881.77 | $47,213.71 | 32 | 85% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 715.46 | $25,863.81 | 0.00 | $- | 715.46 | $25,863.81 | 33 | 105% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 222.28 | $8,035.49 | 0.00 | $- | 222.28 | $8,035.49 | 34 | 128% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 510.80 | $16,754.24 | 0.00 | $- | 510.80 | $16,754.24 | 35 | 105% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 951.22 | $22,448.79 | 0.00 | $- | 951.22 | $22,448.79 | 36 | 110% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 333.00 | $9,823.50 | 0.00 | $- | 333.00 | $9,823.50 | 41 | 101% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 39.60 | $1,298.88 | 0.00 | $- | 39.60 | $1,298.88 | 44 | 198% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 3.00 | $75.00 | 0.00 | $- | 3.00 | $75.00 | 45 | 60% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 39.00 | $3,900.00 | 0.00 | $- | 39.00 | $3,900.00 | 46 | 91% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 48.00 | $7,200.00 | 28.66 | $4,299.00 | 76.66 | $11,499.00 | 48 | 101% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 9.00 | $15,750.00 | 1.00 | $1,750.00 | 10.00 | $17,500.00 | 50 | 111% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 10.00 | $45,000.00 | 0.00 | $- | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $395,046.67 | $7,440.38 | $402,487.05 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $395,046.67 | $7,440.38 | $402,487.05 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 93% | |||||||||||||
79 | 5% RETAINAGE | $19,752.33 | $372.02 | $20,124.35 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $7,068.36 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $7,440.38 | amounting to | $7,068.36 | |||||||||||
86 | This certificate is for work completed through : | November 30, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 7 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.80 | $800.00 | 0.00 | $- | 0.80 | $800.00 | 2 | 80% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 28.00 | $420.00 | 13.00 | $195.00 | 41.00 | $615.00 | 5 | 51% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 14.00 | $16,800.00 | 0.00 | $- | 14.00 | $16,800.00 | 8 | 100% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 33.35 | $110.06 | 0.00 | $- | 33.35 | $110.06 | 10 | 36% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 1.00 | $2,100.00 | 0.00 | $- | 1.00 | $2,100.00 | 13 | 100% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 4,240.84 | $51,271.76 | 0.00 | $- | 4,240.84 | $51,271.76 | 17 | 97% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 5,438.03 | $3,262.82 | 0.00 | $- | 5,438.03 | $3,262.82 | 19 | 98% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 71.40 | $10,710.00 | 4.00 | $600.00 | 75.40 | $11,310.00 | 20 | 67% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 0.00 | $- | 1.00 | $650.00 | 1.00 | $650.00 | 23 | 100% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 11.00 | $7,150.00 | 4.00 | $2,600.00 | 15.00 | $9,750.00 | 24 | 100% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 1.00 | $150.00 | 0.00 | $- | 1.00 | $150.00 | 25 | 50% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 4.00 | $3,000.00 | 0.00 | $- | 4.00 | $3,000.00 | 26 | 200% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 4,906.95 | $28,754.73 | 0.00 | $- | 4,906.95 | $28,754.73 | 27 | 88% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 3,428.60 | $12,000.10 | 2,247.00 | $7,864.50 | 5,675.60 | $19,864.60 | 28 | 102% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 3,428.60 | $12,000.10 | 2,247.00 | $7,864.50 | 5,675.60 | $19,864.60 | 29 | 102% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 21.33 | $383.94 | 40.90 | $736.20 | 62.23 | $1,120.14 | 30 | 40% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 0.00 | $- | 39.20 | $531.16 | 39.20 | $531.16 | 31 | 52% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,881.77 | $47,213.71 | 0.00 | $- | 1,881.77 | $47,213.71 | 32 | 85% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 715.46 | $25,863.81 | 0.00 | $- | 715.46 | $25,863.81 | 33 | 105% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 222.28 | $8,035.49 | 0.00 | $- | 222.28 | $8,035.49 | 34 | 128% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 510.80 | $16,754.24 | 0.00 | $- | 510.80 | $16,754.24 | 35 | 105% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 951.22 | $22,448.79 | 0.00 | $- | 951.22 | $22,448.79 | 36 | 110% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 333.00 | $9,823.50 | 0.00 | $- | 333.00 | $9,823.50 | 41 | 101% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 0.00 | $- | 39.60 | $1,298.88 | 39.60 | $1,298.88 | 44 | 198% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 0.00 | $- | 3.00 | $75.00 | 3.00 | $75.00 | 45 | 60% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 60.00 | $6,000.00 | -21.00 | $(2,100.00) | 39.00 | $3,900.00 | 46 | 91% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 48.00 | $7,200.00 | 0.00 | $- | 48.00 | $7,200.00 | 48 | 63% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 9.00 | $15,750.00 | 0.00 | $- | 9.00 | $15,750.00 | 50 | 100% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 10.00 | $45,000.00 | 0.00 | $- | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $374,731.43 | $20,315.24 | $395,046.67 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $374,731.43 | $20,315.24 | $395,046.67 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 92% | |||||||||||||
79 | 5% RETAINAGE | $18,736.57 | $1,015.76 | $19,752.33 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $19,299.48 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $20,315.24 | amounting to | $19,299.48 | |||||||||||
86 | This certificate is for work completed through : | November 15, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 6 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.80 | $800.00 | 0.00 | $- | 0.80 | $800.00 | 2 | 80% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 28.00 | $420.00 | 0.00 | $- | 28.00 | $420.00 | 5 | 35% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 14.00 | $16,800.00 | 0.00 | $- | 14.00 | $16,800.00 | 8 | 100% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 33.35 | $110.06 | 0.00 | $- | 33.35 | $110.06 | 10 | 36% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 1.00 | $2,100.00 | 0.00 | $- | 1.00 | $2,100.00 | 13 | 100% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 4,240.84 | $51,271.76 | 0.00 | $- | 4,240.84 | $51,271.76 | 17 | 97% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 5,438.03 | $3,262.82 | 0.00 | $- | 5,438.03 | $3,262.82 | 19 | 98% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 57.40 | $8,610.00 | 14.00 | $2,100.00 | 71.40 | $10,710.00 | 20 | 63% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 23 | 0% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 11.00 | $7,150.00 | 0.00 | $- | 11.00 | $7,150.00 | 24 | 73% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 1.00 | $150.00 | 0.00 | $- | 1.00 | $150.00 | 25 | 50% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 1.00 | $750.00 | 3.00 | $2,250.00 | 4.00 | $3,000.00 | 26 | 200% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 4,906.95 | $28,754.73 | 0.00 | $- | 4,906.95 | $28,754.73 | 27 | 88% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 3,428.60 | $12,000.10 | 0.00 | $- | 3,428.60 | $12,000.10 | 28 | 62% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 3,428.60 | $12,000.10 | 0.00 | $- | 3,428.60 | $12,000.10 | 29 | 62% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 0.00 | $- | 21.33 | $383.94 | 21.33 | $383.94 | 30 | 14% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 31 | 0% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,881.77 | $47,213.71 | 0.00 | $- | 1,881.77 | $47,213.71 | 32 | 85% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 715.46 | $25,863.81 | 0.00 | $- | 715.46 | $25,863.81 | 33 | 105% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 222.28 | $8,035.49 | 0.00 | $- | 222.28 | $8,035.49 | 34 | 128% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 510.80 | $16,754.24 | 0.00 | $- | 510.80 | $16,754.24 | 35 | 105% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 951.22 | $22,448.79 | 0.00 | $- | 951.22 | $22,448.79 | 36 | 110% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 333.00 | $9,823.50 | 0.00 | $- | 333.00 | $9,823.50 | 41 | 101% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 44 | 0% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 45 | 0% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 30.00 | $3,000.00 | 30.00 | $3,000.00 | 60.00 | $6,000.00 | 46 | 140% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 48.00 | $7,200.00 | 0.00 | $- | 48.00 | $7,200.00 | 48 | 63% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 9.00 | $15,750.00 | 0.00 | $- | 9.00 | $15,750.00 | 50 | 100% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 10.00 | $45,000.00 | 0.00 | $- | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $366,997.49 | $7,733.94 | $374,731.43 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $366,997.49 | $7,733.94 | $374,731.43 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 87% | |||||||||||||
79 | 5% RETAINAGE | $18,349.87 | $386.70 | $18,736.57 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $7,347.24 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $7,733.94 | amounting to | $7,347.24 | |||||||||||
86 | This certificate is for work completed through : | October 31, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 5 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.80 | $800.00 | 0.00 | $- | 0.80 | $800.00 | 2 | 80% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 28.00 | $420.00 | 0.00 | $- | 28.00 | $420.00 | 5 | 35% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 14.00 | $16,800.00 | 0.00 | $- | 14.00 | $16,800.00 | 8 | 100% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 33.35 | $110.06 | 0.00 | $- | 33.35 | $110.06 | 10 | 36% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 1.00 | $2,100.00 | 0.00 | $- | 1.00 | $2,100.00 | 13 | 100% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 4,240.84 | $51,271.76 | 0.00 | $- | 4,240.84 | $51,271.76 | 17 | 97% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 5,438.03 | $3,262.82 | 0.00 | $- | 5,438.03 | $3,262.82 | 19 | 98% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 57.40 | $8,610.00 | 0.00 | $- | 57.40 | $8,610.00 | 20 | 51% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 23 | 0% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 11.00 | $7,150.00 | 0.00 | $- | 11.00 | $7,150.00 | 24 | 73% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 1.00 | $150.00 | 0.00 | $- | 1.00 | $150.00 | 25 | 50% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 1.00 | $750.00 | 0.00 | $- | 1.00 | $750.00 | 26 | 50% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 4,286.13 | $25,116.72 | 620.82 | $3,638.01 | 4,906.95 | $28,754.73 | 27 | 88% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 3,428.60 | $12,000.10 | 0.00 | $- | 3,428.60 | $12,000.10 | 28 | 62% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 2,599.10 | $9,096.85 | 829.50 | $2,903.25 | 3,428.60 | $12,000.10 | 29 | 62% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 30 | 0% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 31 | 0% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,880.25 | $47,175.57 | 1.52 | $38.14 | 1,881.77 | $47,213.71 | 32 | 85% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 566.96 | $20,495.53 | 148.50 | $5,368.28 | 715.46 | $25,863.81 | 33 | 105% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 192.42 | $6,956.06 | 29.86 | $1,079.44 | 222.28 | $8,035.49 | 34 | 128% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 319.20 | $10,469.76 | 191.60 | $6,284.48 | 510.80 | $16,754.24 | 35 | 105% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 810.06 | $19,117.42 | 141.16 | $3,331.38 | 951.22 | $22,448.79 | 36 | 110% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 30.00 | $2,250.00 | -30.00 | $(2,250.00) | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 333.00 | $9,823.50 | 0.00 | $- | 333.00 | $9,823.50 | 41 | 101% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 44 | 0% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 45 | 0% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 0.00 | $- | 30.00 | $3,000.00 | 30.00 | $3,000.00 | 46 | 70% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 48.00 | $7,200.00 | 0.00 | $- | 48.00 | $7,200.00 | 48 | 63% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 9.00 | $15,750.00 | 0.00 | $- | 9.00 | $15,750.00 | 50 | 100% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 10.00 | $45,000.00 | 0.00 | $- | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $343,604.53 | $23,392.96 | $366,997.49 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $343,604.53 | $23,392.96 | $366,997.49 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 85% | |||||||||||||
79 | 5% RETAINAGE | $17,180.23 | $1,169.65 | $18,349.87 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $22,223.31 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $23,392.96 | amounting to | $22,223.31 | |||||||||||
86 | This certificate is for work completed through : | October 15, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 4 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.80 | $800.00 | 0.00 | $- | 0.80 | $800.00 | 2 | 80% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 28.00 | $420.00 | 0.00 | $- | 28.00 | $420.00 | 5 | 35% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 12.00 | $14,400.00 | 2.00 | $2,400.00 | 14.00 | $16,800.00 | 8 | 100% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 33.35 | $110.06 | 0.00 | $- | 33.35 | $110.06 | 10 | 36% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 0.90 | $1,890.00 | 0.10 | $210.00 | 1.00 | $2,100.00 | 13 | 100% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 3,717.65 | $44,946.39 | 523.19 | $6,325.37 | 4,240.84 | $51,271.76 | 17 | 97% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 4,800.33 | $2,880.20 | 637.70 | $382.62 | 5,438.03 | $3,262.82 | 19 | 98% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 57.40 | $8,610.00 | 0.00 | $- | 57.40 | $8,610.00 | 20 | 51% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 23 | 0% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 11.00 | $7,150.00 | 0.00 | $- | 11.00 | $7,150.00 | 24 | 73% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 1.00 | $150.00 | 0.00 | $- | 1.00 | $150.00 | 25 | 50% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 1.00 | $750.00 | 0.00 | $- | 1.00 | $750.00 | 26 | 50% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 4,286.13 | $25,116.72 | 0.00 | $- | 4,286.13 | $25,116.72 | 27 | 77% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 2,599.10 | $9,096.85 | 829.50 | $2,903.25 | 3,428.60 | $12,000.10 | 28 | 62% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 2,599.10 | $9,096.85 | 0.00 | $- | 2,599.10 | $9,096.85 | 29 | 47% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 30 | 0% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 31 | 0% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,610.96 | $40,419.09 | 269.29 | $6,756.49 | 1,880.25 | $47,175.57 | 32 | 85% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 391.74 | $14,161.55 | 175.21 | $6,333.99 | 566.96 | $20,495.53 | 33 | 83% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 141.17 | $5,103.15 | 51.26 | $1,852.90 | 192.42 | $6,956.06 | 34 | 111% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 319.20 | $10,469.76 | 0.00 | $- | 319.20 | $10,469.76 | 35 | 65% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 623.40 | $14,712.24 | 186.66 | $4,405.18 | 810.06 | $19,117.42 | 36 | 94% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 0.00 | $- | 30.00 | $2,250.00 | 30.00 | $2,250.00 | 39 | 3000% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 175.00 | $5,162.50 | 158.00 | $4,661.00 | 333.00 | $9,823.50 | 41 | 101% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 44 | 0% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 45 | 0% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 46 | 0% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 48.00 | $7,200.00 | 0.00 | $- | 48.00 | $7,200.00 | 48 | 63% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 9.00 | $15,750.00 | 0.00 | $- | 9.00 | $15,750.00 | 50 | 100% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 10.00 | $45,000.00 | 0.00 | $- | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $305,123.74 | $38,480.79 | $343,604.53 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $305,123.74 | $38,480.79 | $343,604.53 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 80% | |||||||||||||
79 | 5% RETAINAGE | $15,256.19 | $1,924.04 | $17,180.23 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $36,556.75 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $38,480.79 | amounting to | $36,556.75 | |||||||||||
86 | This certificate is for work completed through : | September 30, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 3 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1.00 | $1,000.00 | 0.60 | $600.00 | 0.20 | $200.00 | 0.80 | $800.00 | 2 | 80% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14.00 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80.00 | $1,200.00 | 20.00 | $300.00 | 8.00 | $120.00 | 28.00 | $420.00 | 5 | 35% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1.00 | $500.00 | 0.50 | $250.00 | 0.00 | $- | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25.00 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14.00 | $16,800.00 | 12.00 | $14,400.00 | 0.00 | $- | 12.00 | $14,400.00 | 8 | 86% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1.00 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93.40 | $308.22 | 0.00 | $- | 33.35 | $110.06 | 33.35 | $110.06 | 10 | 36% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.70 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5.00 | $125.00 | 5.00 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1.00 | $2,100.00 | 0.90 | $1,890.00 | 0.00 | $- | 0.90 | $1,890.00 | 13 | 90% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1.00 | $10.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1.00 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10.00 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372.00 | $52,857.48 | 2,944.65 | $35,600.82 | 773.00 | $9,345.57 | 3,717.65 | $44,946.39 | 17 | 85% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788.00 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574.00 | $3,344.40 | 3,480.33 | $2,088.20 | 1,320.00 | $792.00 | 4,800.33 | $2,880.20 | 19 | 86% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.80 | $16,920.00 | 44.10 | $6,615.00 | 13.30 | $1,995.00 | 57.40 | $8,610.00 | 20 | 51% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24.00 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10.00 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1.00 | $650.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 23 | 0% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15.00 | $9,750.00 | 8.00 | $5,200.00 | 3.00 | $1,950.00 | 11.00 | $7,150.00 | 24 | 73% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2.00 | $300.00 | 0.00 | $- | 1.00 | $150.00 | 1.00 | $150.00 | 25 | 50% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2.00 | $1,500.00 | 1.00 | $750.00 | 0.00 | $- | 1.00 | $750.00 | 26 | 50% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574.00 | $32,663.64 | 3,480.33 | $20,394.73 | 805.80 | $4,721.99 | 4,286.13 | $25,116.72 | 27 | 77% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 0.00 | $- | 2,599.10 | $9,096.85 | 2,599.10 | $9,096.85 | 28 | 47% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574.00 | $19,509.00 | 0.00 | $- | 2,599.10 | $9,096.85 | 2,599.10 | $9,096.85 | 29 | 47% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.10 | $2,773.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 30 | 0% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76.00 | $1,029.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 31 | 0% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208.00 | $55,398.72 | 1,126.69 | $28,268.65 | 484.27 | $12,150.43 | 1,610.96 | $40,419.09 | 32 | 73% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684.30 | $24,737.45 | 317.47 | $11,476.54 | 74.27 | $2,685.01 | 391.74 | $14,161.55 | 33 | 57% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.70 | $6,279.26 | 119.89 | $4,334.02 | 21.28 | $769.13 | 141.17 | $5,103.15 | 34 | 81% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 488.70 | $16,029.36 | 319.20 | $10,469.76 | 0.00 | $- | 319.20 | $10,469.76 | 35 | 65% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863.00 | $20,366.80 | 384.02 | $9,062.87 | 239.38 | $5,649.37 | 623.40 | $14,712.24 | 36 | 72% | |
44 | 37 | Concrete Steps | m | $90.00 | 4.80 | $432.00 | 2.96 | $266.40 | 0.00 | $- | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9.00 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1.00 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1.00 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331.00 | $9,764.50 | 175.00 | $5,162.50 | 0.00 | $- | 175.00 | $5,162.50 | 41 | 53% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871.00 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1.00 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20.00 | $656.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 44 | 0% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5.00 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 45 | 0% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43.00 | $4,300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 46 | 0% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5.00 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.20 | $11,430.00 | 48.00 | $7,200.00 | 0.00 | $- | 48.00 | $7,200.00 | 48 | 63% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31.00 | $1,090.27 | 8.00 | $281.36 | 0.00 | $- | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9.00 | $15,750.00 | 11.00 | $19,250.00 | -2.00 | $(3,500.00) | 9.00 | $15,750.00 | 50 | 100% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1.00 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10.00 | $45,000.00 | 11.00 | $49,500.00 | -1.00 | $(4,500.00) | 10.00 | $45,000.00 | 52 | 100% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 1.00 | $300.00 | 1.00 | $300.00 | 53 | 100% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1.00 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $253,991.49 | $51,132.25 | $305,123.74 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $253,991.49 | $51,132.25 | $305,123.74 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 71% | |||||||||||||
79 | 5% RETAINAGE | $12,699.57 | $2,556.61 | $15,256.19 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $48,575.64 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $51,132.25 | amounting to | $48,575.64 | |||||||||||
86 | This certificate is for work completed through : | September 15, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 2 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.40 | $400.00 | 0.20 | $200.00 | 0.60 | $600.00 | 2 | 60% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 8 | $466.20 | 25.92 | $1,555.20 | 0.00 | $- | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 0.00 | $- | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 0.00 | $- | 20.00 | $300.00 | 20.00 | $300.00 | 5 | 25% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.00 | $- | 0.50 | $250.00 | 0.50 | $250.00 | 6 | 50% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 12.00 | $14,400.00 | 0.00 | $- | 12.00 | $14,400.00 | 8 | 86% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93 | $308.22 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 10 | 0% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 146 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 5.00 | $125.00 | 5.00 | $125.00 | 12 | 100% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.90 | $1,890.00 | 0.00 | $- | 0.90 | $1,890.00 | 13 | 90% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 1.00 | $10.00 | -1.00 | $(10.00) | 0.00 | $- | 14 | 0% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 0.00 | $- | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 2,944.65 | $35,600.82 | 0.00 | $- | 2,944.65 | $35,600.82 | 17 | 67% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 0.00 | $- | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 3,480.33 | $2,088.20 | 0.00 | $- | 3,480.33 | $2,088.20 | 19 | 62% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 113 | $16,920.00 | 0.00 | $- | 44.10 | $6,615.00 | 44.10 | $6,615.00 | 20 | 39% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 23 | 0% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 0.00 | $- | 8.00 | $5,200.00 | 8.00 | $5,200.00 | 24 | 53% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 25 | 0% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 0.00 | $- | 1.00 | $750.00 | 1.00 | $750.00 | 26 | 50% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 3,480.33 | $20,394.73 | 0.00 | $- | 3,480.33 | $20,394.73 | 27 | 62% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 28 | 0% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 29 | 0% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154 | $2,773.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 30 | 0% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 31 | 0% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 822.33 | $20,632.26 | 304.36 | $7,636.39 | 1,126.69 | $28,268.65 | 32 | 51% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684 | $24,737.45 | 128.18 | $4,633.71 | 189.29 | $6,842.83 | 317.47 | $11,476.54 | 33 | 46% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 174 | $6,279.26 | 72.37 | $2,616.18 | 47.52 | $1,717.85 | 119.89 | $4,334.02 | 34 | 69% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 489 | $16,029.36 | 319.20 | $10,469.76 | 0.00 | $- | 319.20 | $10,469.76 | 35 | 65% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 228.70 | $5,397.32 | 155.32 | $3,665.55 | 384.02 | $9,062.87 | 36 | 44% | |
44 | 37 | Concrete Steps | m | $90.00 | 5 | $432.00 | 0.00 | $- | 2.96 | $266.40 | 2.96 | $266.40 | 37 | 62% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 0.00 | $- | 175.00 | $5,162.50 | 175.00 | $5,162.50 | 41 | 53% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 44 | 0% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 45 | 0% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 46 | 0% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76 | $11,430.00 | 0.00 | $- | 48.00 | $7,200.00 | 48.00 | $7,200.00 | 48 | 63% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 0.00 | $- | 8.00 | $281.36 | 8.00 | $281.36 | 49 | 26% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 5.00 | $8,750.00 | 6.00 | $10,500.00 | 11.00 | $19,250.00 | 50 | 122% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 5.00 | $22,500.00 | 6.00 | $27,000.00 | 11.00 | $49,500.00 | 52 | 110% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 53 | 0% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $170,288.61 | $83,702.89 | $253,991.49 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $170,288.61 | $83,702.89 | $253,991.49 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 59% | |||||||||||||
79 | 5% RETAINAGE | $8,514.43 | $4,185.14 | $12,699.57 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $79,517.74 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $83,702.89 | amounting to | $79,517.74 | |||||||||||
86 | This certificate is for work completed through : | August 15, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | PROGRESS PAYMENT CERTIFICATE NO. 1 | ||||||||||||||
2 | for | ||||||||||||||
3 | Lents Phase I LID | ||||||||||||||
5 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | |||||||||||
6 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||
8 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 0.00 | $- | 1.00 | $17,000.00 | 1.00 | $17,000.00 | 1 | 100% | Complete |
9 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.00 | $- | 0.40 | $400.00 | 0.40 | $400.00 | 2 | 40% | |
10 | 3 | Temporary Signs | m2 | $60.00 | 8 | $466.20 | 0.00 | $- | 25.92 | $1,555.20 | 25.92 | $1,555.20 | 3 | 334% | |
11 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 0.00 | $- | 13.00 | $1,430.00 | 13.00 | $1,430.00 | 4 | 93% | |
12 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 5 | 0% | |
13 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 6 | 0% | |
14 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 7 | 0% | |
15 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 0.00 | $- | 12.00 | $14,400.00 | 12.00 | $14,400.00 | 8 | 86% | |
16 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 9 | 0% | |
17 | 10 | Removal of Curbs | m | $3.30 | 93 | $308.22 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 10 | 0% | |
18 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 146 | $1,129.18 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 11 | 0% | |
19 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 12 | 0% | |
20 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.00 | $- | 0.90 | $1,890.00 | 0.90 | $1,890.00 | 13 | 90% | |
21 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 1.00 | $10.00 | 1.00 | $10.00 | 14 | 100% | |
22 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 0.00 | $- | 2.00 | $200.00 | 2.00 | $200.00 | 15 | 200% | |
23 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 0.00 | $- | 10.00 | $10.00 | 10.00 | $10.00 | 16 | 100% | |
24 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 0.00 | $- | 2,944.65 | $35,600.82 | 2,944.65 | $35,600.82 | 17 | 67% | |
25 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 0.00 | $- | 105.95 | $310.43 | 105.95 | $310.43 | 18 | 4% | |
26 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 0.00 | $- | 3,480.33 | $2,088.20 | 3,480.33 | $2,088.20 | 19 | 62% | |
27 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 113 | $16,920.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 20 | 0% | |
28 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 21 | 0% | |
29 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 22 | 0% | |
30 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 23 | 0% | |
31 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 24 | 0% | |
32 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 25 | 0% | |
33 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 26 | 0% | |
34 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 0.00 | $- | 3,480.33 | $20,394.73 | 3,480.33 | $20,394.73 | 27 | 62% | |
35 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 28 | 0% | |
36 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 29 | 0% | |
37 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154 | $2,773.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 30 | 0% | |
38 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 31 | 0% | |
39 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 0.00 | $- | 822.33 | $20,632.26 | 822.33 | $20,632.26 | 32 | 37% | |
40 | 33 | Concrete Driveways | m2 | $36.15 | 684 | $24,737.45 | 0.00 | $- | 128.18 | $4,633.71 | 128.18 | $4,633.71 | 33 | 19% | |
41 | 34 | Concrete Driveway Connection | m2 | $36.15 | 174 | $6,279.26 | 0.00 | $- | 72.37 | $2,616.18 | 72.37 | $2,616.18 | 34 | 42% | |
42 | 35 | Concrete Curb Type A | m | $32.80 | 489 | $16,029.36 | 0.00 | $- | 319.20 | $10,469.76 | 319.20 | $10,469.76 | 35 | 65% | |
43 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 0.00 | $- | 228.70 | $5,397.32 | 228.70 | $5,397.32 | 36 | 27% | |
44 | 37 | Concrete Steps | m | $90.00 | 5 | $432.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 37 | 0% | |
45 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 38 | 0% | |
46 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 39 | 0% | |
47 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 40 | 0% | |
48 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 41 | 0% | |
49 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 42 | 0% | |
50 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 43 | 0% | |
51 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 44 | 0% | |
52 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 45 | 0% |
53 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 46 | 0% | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
54 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 47 | 0% | |
55 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76 | $11,430.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 48 | 0% | |
56 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 49 | 0% | |
57 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 0.00 | $- | 5.00 | $8,750.00 | 5.00 | $8,750.00 | 50 | 56% | |
58 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 51 | 0% | |
59 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 0.00 | $- | 5.00 | $22,500.00 | 5.00 | $22,500.00 | 52 | 50% | |
60 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 53 | 0% | |
61 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0.00 | $- | 0.00 | $- | 54 | 0% | |
64 | TOTAL | $430,663.04 | $- | $170,288.61 | $170,288.61 | ||||||||||
66 | CHANGE ORDERS | ||||||||||||||
67 | $- | 0 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO1 | #DIV/0! | ||||
68 | $- | 0 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO2 | #DIV/0! | ||||
69 | $- | 0 | $- | 0.00 | $- | 0.00 | $- | 0.00 | $- | CO3 | #DIV/0! | ||||
71 | TOTAL CHANGE ORDERS | $- | $- | $- | $- | ||||||||||
73 | TOTAL ALL ITEMS | $430,663.04 | $- | $170,288.61 | $170,288.61 | ||||||||||
77 | DOLLAR PERCENT COMPLETE | 40% | |||||||||||||
79 | 5% RETAINAGE | $- | $8,514.43 | $8,514.43 | |||||||||||
81 | PAYMENT THIS CERTIFICATE | $161,774.18 | |||||||||||||
84 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any | ||||||||||||||
85 | previous certificates. The amount to be paid said contractor under this certificate is 95.00 per cent of : | $170,288.61 | amounting to | $161,774.18 | |||||||||||
86 | This certificate is for work completed through : | August 15, 2001. | |||||||||||||
89 | Approved: _____________________________________________ Date: __________ | Approved: ______________________________________________ Date: __________ | |||||||||||||
90 | Contract Manager | City Engineer |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 6 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 100% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.80 | $800.00 | 80% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 334% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 93% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 28.00 | $420.00 | 35% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.50 | $250.00 | 50% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 12.00 | $14,400.00 | 86% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 33.35 | $110.06 | 36% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 5.00 | $125.00 | 100% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.90 | $1,890.00 | 90% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 0% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 200% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 100% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 3,717.65 | $44,946.39 | 85% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 4% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 4,800.33 | $2,880.20 | 86% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 57.40 | $8,610.00 | 51% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 11.00 | $7,150.00 | 73% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 1.00 | $150.00 | 50% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 1.00 | $750.00 | 50% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 4,906.95 | $28,754.73 | 88% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 2,599.10 | $9,096.85 | 47% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 3,428.60 | $12,000.10 | 62% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 0.00 | $- | 0% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 1,612.48 | $40,457.22 | 73% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 540.24 | $19,529.82 | 79% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 171.03 | $6,182.59 | 98% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 510.80 | $16,754.24 | 105% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 764.56 | $18,043.62 | 89% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 2.96 | $266.40 | 62% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 175.00 | $5,162.50 | 53% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 48.00 | $7,200.00 | 63% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 8.00 | $281.36 | 26% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 9.00 | $15,750.00 | 100% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 10.00 | $45,000.00 | 100% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 1.00 | $300.00 | 100% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $327,766.70 | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $327,766.70 | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 5 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 100% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.80 | $800.00 | 80% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 334% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 93% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 28.00 | $420.00 | 35% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.50 | $250.00 | 50% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 14.00 | $16,800.00 | 100% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 33.35 | $110.06 | 36% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 5.00 | $125.00 | 100% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 1.00 | $2,100.00 | 100% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 0% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 200% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 100% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 4,240.84 | $51,271.76 | 97% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 4% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 5,438.03 | $3,262.82 | 98% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 57.40 | $8,610.00 | 51% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 11.00 | $7,150.00 | 73% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 1.00 | $150.00 | 50% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 1.00 | $750.00 | 50% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 4,286.13 | $25,116.72 | 77% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 3,428.60 | $12,000.10 | 62% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 2,599.10 | $9,096.85 | 47% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 0.00 | $- | 0% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 1,880.25 | $47,175.57 | 85% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 566.96 | $20,495.53 | 83% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 192.42 | $6,956.06 | 111% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 319.20 | $10,469.76 | 65% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 810.06 | $19,117.42 | 94% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 2.96 | $266.40 | 62% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 30.00 | $2,250.00 | 3000% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 333.00 | $9,823.50 | 101% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 48.00 | $7,200.00 | 63% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 8.00 | $281.36 | 26% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 9.00 | $15,750.00 | 100% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 10.00 | $45,000.00 | 100% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 1.00 | $300.00 | 100% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $343,604.53 | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $343,604.53 | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 4 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 100% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.80 | $800.00 | 80% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 334% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 93% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 28.00 | $420.00 | 35% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.50 | $250.00 | 50% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 12.00 | $14,400.00 | 86% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 33.35 | $110.06 | 36% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 5.00 | $125.00 | 100% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.90 | $1,890.00 | 90% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 0% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 200% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 100% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 3,717.65 | $44,946.39 | 85% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 4% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 4,800.33 | $2,880.20 | 86% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 57.40 | $8,610.00 | 51% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 11.00 | $7,150.00 | 73% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 1.00 | $150.00 | 50% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 1.00 | $750.00 | 50% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 4,286.13 | $25,116.72 | 77% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 2,599.10 | $9,096.85 | 47% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 2,599.10 | $9,096.85 | 47% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 0.00 | $- | 0% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 1,610.96 | $40,419.09 | 73% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 391.74 | $14,161.55 | 57% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 141.17 | $5,103.15 | 81% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 319.20 | $10,469.76 | 65% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 623.40 | $14,712.24 | 72% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 2.96 | $266.40 | 62% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 175.00 | $5,162.50 | 53% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 48.00 | $7,200.00 | 63% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 8.00 | $281.36 | 26% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 9.00 | $15,750.00 | 100% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 10.00 | $45,000.00 | 100% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 1.00 | $300.00 | 100% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $305,123.74 | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $305,123.74 | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 2 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 100% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.60 | $600.00 | 60% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 334% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 93% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 20.00 | $300.00 | 25% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.50 | $250.00 | 50% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 12.00 | $14,400.00 | 86% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 0.00 | $- | 0% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 5.00 | $125.00 | 100% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.90 | $1,890.00 | 90% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 0% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 200% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 100% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 2,944.65 | $35,600.82 | 67% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 4% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 3,480.33 | $2,088.20 | 62% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 44.10 | $6,615.00 | 39% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 8.00 | $5,200.00 | 53% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 0.00 | $- | 0% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 1.00 | $750.00 | 50% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 3,480.33 | $20,394.73 | 62% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 0.00 | $- | 0% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 1,126.69 | $28,268.65 | 51% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 317.47 | $11,476.54 | 46% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 119.89 | $4,334.02 | 69% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 319.20 | $10,469.76 | 65% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 384.02 | $9,062.87 | 44% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 2.96 | $266.40 | 62% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 175.00 | $5,162.50 | 53% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 48.00 | $7,200.00 | 63% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 8.00 | $281.36 | 26% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 11.00 | $19,250.00 | 122% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 11.00 | $49,500.00 | 110% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $253,991.49 | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $253,991.49 | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 2 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 1.00 | $17,000.00 | 100% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.40 | $400.00 | 40% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 25.92 | $1,555.20 | 334% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 13.00 | $1,430.00 | 93% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 0.00 | $- | 0% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.00 | $- | 0% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 12.00 | $14,400.00 | 86% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 0.00 | $- | 0% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.90 | $1,890.00 | 90% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 1.00 | $10.00 | 100% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 2.00 | $200.00 | 200% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 10.00 | $10.00 | 100% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 2,944.65 | $35,600.82 | 67% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 105.95 | $310.43 | 4% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 3,480.33 | $2,088.20 | 62% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 0.00 | $- | 0% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 0.00 | $- | 0% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 0.00 | $- | 0% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 0.00 | $- | 0% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 3,480.33 | $20,394.73 | 62% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 0.00 | $- | 0% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 822.33 | $20,632.26 | 37% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 128.18 | $4,633.71 | 19% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 72.37 | $2,616.18 | 42% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 319.20 | $10,469.76 | 65% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 228.70 | $5,397.32 | 27% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 0.00 | $- | 0% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 0.00 | $- | 0% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 0.00 | $- | 0% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 0.00 | $- | 0% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 5.00 | $8,750.00 | 56% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 5.00 | $22,500.00 | 50% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $170,288.61 | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $170,288.61 | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CITY OF PORTLAND, OREGON | |||||||||||
2 | BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT | |||||||||||
3 | INSPECTOR'S WORKSHEET: PROGRESS PAYMENT CERTIFICATE NO. 1 | |||||||||||
4 | ||||||||||||
5 | for Lents Phase I LID | |||||||||||
6 | ||||||||||||
7 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | % | THIS CERTIFICATE | ||||||||
8 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | Complete | QUANTITY | NOTES | |
9 | 1 | Mobilization | ls | $17,000.00 | 1 | $17,000.00 | 0.00 | $- | 0% | |||
10 | 2 | Temporary Protection & Direction of Traffic | ls | $1,000.00 | 1 | $1,000.00 | 0.00 | $- | 0% | |||
11 | 3 | Temporary Signs | m2 | $60.00 | 7.77 | $466.20 | 0.00 | $- | 0% | |||
12 | 4 | Temporary Barricades | ea | $110.00 | 14 | $1,540.00 | 0.00 | $- | 0% | |||
13 | 5 | Flaggers | hr | $15.00 | 80 | $1,200.00 | 0.00 | $- | 0% | |||
14 | 6 | Temporary Erosion Control | ls | $500.00 | 1 | $500.00 | 0.00 | $- | 0% | |||
15 | 7 | Inlet Protection | ea | $50.00 | 25 | $1,250.00 | 0.00 | $- | 0% | |||
16 | 8 | Gravel Entrance | ea | $1,200.00 | 14 | $16,800.00 | 0.00 | $- | 0% | |||
17 | 9 | Removal of Structures & Obstructions | ls | $1.00 | 1 | $1.00 | 0.00 | $- | 0% | |||
18 | 10 | Removal of Curbs | m | $3.30 | 93.4 | $308.22 | 0.00 | $- | 0% | |||
19 | 11 | Removal of Walks and Driveways | m2 | $7.75 | 145.7 | $1,129.18 | 0.00 | $- | 0% | |||
20 | 12 | Removal of Inlets | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
21 | 13 | Clearing and Grubbing | ls | $2,100.00 | 1 | $2,100.00 | 0.00 | $- | 0% | |||
22 | 14 | Contingent Tree Removal, 0mm - 200mm | ea | $10.00 | 1 | $10.00 | 0.00 | $- | 0% | |||
23 | 15 | Contingent Tree Removal, 200mm - 510mm | ea | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
24 | 16 | Exploratory Tree Root Excavation | hr | $1.00 | 10 | $10.00 | 0.00 | $- | 0% | |||
25 | 17 | General Excavation | m3 | $12.09 | 4372 | $52,857.48 | 0.00 | $- | 0% | |||
26 | 18 | 300mm Subgrade Stabilization | m2 | $2.93 | 2788 | $8,168.84 | 0.00 | $- | 0% | |||
27 | 19 | Subgrade Geotextile | m2 | $0.60 | 5574 | $3,344.40 | 0.00 | $- | 0% | |||
28 | 20 | 300mm Inlet Pipe, Complete | m | $150.00 | 112.8 | $16,920.00 | 0.00 | $- | 0% | |||
29 | 21 | Extra for Pipe Under Pavement for Bid Item 20 | m | $35.17 | 24 | $844.08 | 0.00 | $- | 0% | |||
30 | 22 | 75mm Drain Pipe (Bid Only) | m | $20.00 | 10 | $200.00 | 0.00 | $- | 0% | |||
31 | 23 | Concrete Inlets Type G-1 | ea | $650.00 | 1 | $650.00 | 0.00 | $- | 0% | |||
32 | 24 | Concrete Inlets Type CG-2 | ea | $650.00 | 15 | $9,750.00 | 0.00 | $- | 0% | |||
33 | 25 | Adjust Manholes | ea | $150.00 | 2 | $300.00 | 0.00 | $- | 0% | |||
34 | 26 | Reconstructing Manholes | ea | $750.00 | 2 | $1,500.00 | 0.00 | $- | 0% | |||
35 | 27 | Aggregate Base (200mm Thick) | m2 | $5.86 | 5574 | $32,663.64 | 0.00 | $- | 0% | |||
36 | 28 | Standard Duty Class "B" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0% | |||
37 | 29 | Standard Duty Class "C" A.C. (40mm Thick) | m2 | $3.50 | 5574 | $19,509.00 | 0.00 | $- | 0% | |||
38 | 30 | Asphalt Driveway Connections | m2 | $18.00 | 154.1 | $2,773.80 | 0.00 | $- | 0% | |||
39 | 31 | Asphalt Sidewalk | m2 | $13.55 | 76 | $1,029.80 | 0.00 | $- | 0% | |||
40 | 32 | Concrete Walks | m2 | $25.09 | 2208 | $55,398.72 | 0.00 | $- | 0% | |||
41 | 33 | Concrete Driveways | m2 | $36.15 | 684.3 | $24,737.45 | 0.00 | $- | 0% | |||
42 | 34 | Concrete Driveway Connection | m2 | $36.15 | 173.7 | $6,279.26 | 0.00 | $- | 0% | |||
43 | 35 | Concrete Curb Type A | m | $32.80 | 488.7 | $16,029.36 | 0.00 | $- | 0% | |||
44 | 36 | Concrete Curb Type C | m | $23.60 | 863 | $20,366.80 | 0.00 | $- | 0% | |||
45 | 37 | Concrete Steps | m | $90.00 | 4.8 | $432.00 | 0.00 | $- | 0% | |||
46 | 38 | Remove & Re-install Existing Signs | ea | $75.00 | 9 | $675.00 | 0.00 | $- | 0% | |||
47 | 39 | Sign Support Footings (Bid Only) | ea | $75.00 | 1 | $75.00 | 0.00 | $- | 0% | |||
48 | 40 | Pipe Sign Posts (Bid Only) | ea | $15.00 | 1 | $15.00 | 0.00 | $- | 0% | |||
49 | 41 | Topsoil | m3 | $29.50 | 331 | $9,764.50 | 0.00 | $- | 0% | |||
50 | 42 | Seeded Lawn | m2 | $0.55 | 1871 | $1,029.05 | 0.00 | $- | 0% |
51 | 43 | Bark Mulch | m3 | $100.00 | 1 | $100.00 | 0.00 | $- | 0% | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 44 | Removing & Rebuilding Fence (Bid Only) | m | $32.80 | 20 | $656.00 | 0.00 | $- | 0% | |||
53 | 45 | Replacement Mailboxes (Bid Only) | ea | $25.00 | 5 | $125.00 | 0.00 | $- | 0% | |||
54 | 46 | Relocate Mailbox with new Post | ea | $100.00 | 43 | $4,300.00 | 0.00 | $- | 0% | |||
55 | 47 | Install Funding Sign | ea | $200.00 | 5 | $1,000.00 | 0.00 | $- | 0% | |||
56 | 48 | 300mm Storm Sewer Pipe, Complete | m | $150.00 | 76.2 | $11,430.00 | 0.00 | $- | 0% | |||
57 | 49 | Extra for Pipe Under Pavement for Bid Item 48 | m | $35.17 | 31 | $1,090.27 | 0.00 | $- | 0% | |||
58 | 50 | Sedimentation Manholes, 3 m Deep | ea | $1,750.00 | 9 | $15,750.00 | 0.00 | $- | 0% | |||
59 | 51 | Sed. Manhole in Location of Exist. Sump | ea | $2,250.00 | 1 | $2,250.00 | 0.00 | $- | 0% | |||
60 | 52 | Concrete Sumps, 9m Deep | ea | $4,500.00 | 10 | $45,000.00 | 0.00 | $- | 0% | |||
61 | 53 | Abandon Manhole | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
62 | 54 | Abandon Sump | ea | $300.00 | 1 | $300.00 | 0.00 | $- | 0% | |||
63 | ||||||||||||
64 | TOTAL BID ITEMS | $430,663.04 | $- | |||||||||
65 | CHANGE ORDERS | |||||||||||
66 | CCO # | $- | 0.00 | $- | ||||||||
67 | CCO # | $- | 0.00 | $- | ||||||||
68 | TOTAL CHANGE ORDERS | $- | $- | |||||||||
69 | ||||||||||||
70 | GRAND TOTAL (BI and CCO's) | $430,663.04 | $- | |||||||||
71 | ||||||||||||
72 |
![]() |
|||||||||||
73 | ||||||||||||
74 | ||||||||||||
75 | ||||||||||||
76 | ||||||||||||
77 |
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | ||||||||||||
2 |
![]() |
|||||||||||
3 | ||||||||||||
4 | ||||||||||||
5 | ||||||||||||
6 | ||||||||||||
7 | ||||||||||||
8 | ||||||||||||
9 | TOTAL ORIGINAL CONTRACT | PRIOR CERTIFICATES | THIS CERTIFICATE | TOTAL TO DATE | ||||||||
10 | NO. | ITEMS OF WORK AND MATERIALS | UNIT | UNIT PRICE | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT |
11 | ||||||||||||
12 | 1 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
13 | 2 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
14 | 3 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
15 | 4 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
16 | 5 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
17 | 6 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
18 | 7 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
19 | 8 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
20 | 9 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
21 | 10 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
22 | 11 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
23 | 12 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
24 | 13 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
25 | 14 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
26 | 15 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
27 | 16 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
28 | 17 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
29 | 18 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
30 | 19 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
31 | 20 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
32 | 21 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
33 | 22 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
34 | 23 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
35 | 24 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
36 | 25 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
37 | 26 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
38 | 27 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
39 | 28 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
40 | 29 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
41 | 30 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
42 | 31 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
43 | 32 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
44 | 33 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
45 | 34 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
46 | 35 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
47 | 36 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
48 | 37 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
49 | 38 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
50 | 39 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- |
51 | 40 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|
52 | 41 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
53 | 42 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
54 | 43 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
55 | 44 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
56 | 45 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
57 | 46 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
58 | 47 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
59 | 48 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
60 | 49 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
61 | 50 | $- | #REF! | #REF! | 0.00 | $- | 0.00 | $- | 0.00 | $- | ||
62 | ||||||||||||
63 | ||||||||||||
64 | TOTAL | #REF! | $- | $- | $- | |||||||
65 | ||||||||||||
66 | CHANGE ORDERS | |||||||||||
67 | ||||||||||||
68 | ||||||||||||
69 | ||||||||||||
70 | ||||||||||||
71 | TOTAL ALL ITEMS | #REF! | $- | $- | $- | |||||||
72 | ||||||||||||
73 | DOLLAR PERCENT COMPLETE | #REF! | ||||||||||
74 | ||||||||||||
75 | PERCENT OVER/UNDER CONTRACT | #REF! | ||||||||||
76 | ||||||||||||
77 | THIS CERTIFICATE + PRIOR CERTIFICATES 5% RETAINAGE = | $- | ||||||||||
78 | ||||||||||||
79 | PAYMENT THIS CERTIFICATE | $- | ||||||||||
80 | ||||||||||||
81 | I, Brant Williams, P.E., and City Engineer, hereby certify that none of the work or materials which is designated under the heading "THIS CERTIFICATE" has been included in any previous certificates. | |||||||||||
82 | The amount to be paid said contractor under this certificate is: | $0.00 | plus all retainage withheld for the length of the contract amounting to | $0.00 | for a total of | $0.00 | ||||||
83 | This certificate is for work completed through : | Month XX, 2001. | ||||||||||
84 | ||||||||||||
85 | ||||||||||||
86 | Approved: _____________________________________________ Date: __________ Approved: ______________________________________________ Date: __________ | |||||||||||
87 | Contract Manager | City Engineer |