1 CITY OF PORTLAND, OREGON
2 BUREAU OF TRANSPORTATION ENGINEERING AND DEVELOPMENT
3            
4    
     
5            
6            
7            
8            
9            
10            
11 Construction          
12   Parker Northwest Paving Company        
13     Contract   $447,374.75  
14     Change Order #1: Retaining Wall   $1,948.95  
15   Construction Total     $449,323.70  
16            
17 Engineering          
18   Design Engineering     $151,997.55  
19   Construction Engineering     $38,012.75  
20   Engineering Total     $190,010.30  
21            
22 Project Management       $80,571.30  
23            
24 SUBTOTAL INCURRED COSTS (already billed to PDC)         $719,905.30
25            
26 Auditor's Costs          
27   LID Construction Fund - Progress Payment Interest through 7/03/02     $7,384.30  
28   LID Construction Fund - Superintendence     $3,185.53  
29   Recording     $1,540.00  
30         $12,109.83  
31            
32 Construction          
33   J.P. Contractors, Inc. (street trees)     $47,344.00  
34         $47,344.00  
35            
36 Project Management          
37   Advertising for Time & Manner Ordinance     $125.00  
38   Project Closeout     $3,309.39  
39         $3,434.39  
40            
41 Overhead          
42   Administrative overhead on project management and engineering @ 40.00%     $109,556.40  
43         $109,556.40  
44            
45 SUBTOTAL ESTIMATED COSTS (to be billed to PDC under terms of I.A.A.)         $172,444.62
46            
47 TOTAL PROJECT COSTS         $892,349.92
48            
49            
50 Property Owner Share          
51   Estimated assessment at LID formation     $219,562.90  
52   Increase (decrease) from estimated to final assessment     $-  
53   Final assessment     $219,562.90  
54            
55   Recording fees     $1,540.00  
56   Total Local Improvement District billing       $221,102.90
57            
58 Other Funding          
59   Portland Development Commission     $614,296.20  
60   Portland Office of Transportation (FY2000 & FY2001 overhead)     $56,950.82  
61           $671,247.02
62            
63 TOTAL PROJECT FUNDING         $892,349.92