A B F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH AI AJ AK AL AM AN
1 PHASE I RESPONSIBILITY       2002                 2003                   2004        
2 Through June 30, 2003 MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
3           PHASE I                               PHASE II                  
4 GRANT APPLICATION HAP       X X X X                                                        
5               X-SITE LAYOUT                                                          
6 PUBLIC COORDINATION HAP TEAM   X X X X X X X X X X X X X                                          
8 PLANNING/TAC PM       X X X X X                                                      
10 DESIGN ASSISTANCE BTED-DM; EP; LG     X X X X X                                                        
12 SITE SURVEY BTED-SUR-Forestry   X X X X                                                            
13 Includes Tree Survey           X-Base Map                                                            
14 Preliminary Grading Plan               X X X                                                    
16 LAND USE REVIEW HAP ARCH/BTED-ESD                                                                      
17 Subdivision Pre-Application                 X -Conference                                                      
18 Tentative Subdivision Development                   X X X X                                              
19 and review by HUD                                                                        
20 Subdivision Application                         X-Application to OPDR                                              
21 OPDR Review                         X X X X                                        
22 Preliminary Plat Approval                                 X - Preliminary Approval                                      
23 Final Plat Application                                   X                                    
24 OPDR Review                                   X X X X                              
25 Final Approval                                         X - Final Approval                              
27 STREET or PLAT VACATION HAP/BTED-RWA             X X X X X X X X X X X                                    
28 Concurrent with Land Use Review                         X-Planning Commission                                              
29                               X-Council                                          
31 UTILITY COORDINATION PM             X X X X X X X                                            
33 TRAFFIC STUDY CONSULTANT             X X X X                                                  
35 PRELIMINARY STREET DESIGN BTED-CDS       X X X X X X X X X X X X X                                      
37 SITE DEMOLITION HAP                               ? X X X                                
39 PHASE II WORK SCOPE                               X X                                      